China Mobile (Gansu Qingyang) Data Center

Qingyang, Gansu, China · Qingyang market · location approximate to district level

Also listed as 中国移动(甘肃·庆阳)数据中心, China Mobile Gansu Qingyang Green Intelligent Computing Center, 中国移动(甘肃·庆阳)绿色智算中心, China Mobile Qingyang N01 and China Mobile Qingyang B01.

China Mobile (Gansu Qingyang) Data Center is a data center project in Qingyang, China, operated by China Mobile Gansu (中国移动通信集团甘肃有限公司). It is operational and expanding. It is planned for 200 MW of IT load.

Latest change on record: moved to expanding on 10 June 2025. Record last checked against its sources on 14 October 2026.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
200 MW
Running now
Not disclosed
Operators rarely publish this
Operator
China Mobile Gansu (中国移动通信集团甘肃有限公司)
Telco
AI workloads
Confirmed
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Qingyang holds 8 active projects with 395 MW of planned IT load between them, and China Mobile (Gansu Qingyang) Data Center ranks first by planned capacity. Of those, 3 are operational and expanding, 4 are under construction and 1 is announced only. No third party publishes a colocation vacancy rate for Qingyang, and ArusGrid does not estimate one.

China Mobile has 11 others in China tracked by ArusGrid, including China Mobile Zhongwei Data Center, Park B, China Mobile Hohhot Data Center and China Mobile Zhongwei Data Center, Xuanhe Park. It sits on the China Mobile Qingyang East Data West Computing campus. Named users of the compute are Meitu, Infinigence AI (无问芯穹), Capital Online (首都在线), Kingsoft Cloud (金山云), Alibaba, MiniMax, Moonshot AI (Kimi) and Gansu Yisuan (甘肃亿算, Yitian Intelligent subsidiary) (reported, unconfirmed).

The build is phased. N01 prefabricated intelligent computing building is operational with a 2024 target; N02 steel-frame building is operational with a 2024 target; B01, largest single building in the park, 30MW total IT power at 30 MW is operational with a 2025 target. The dated record runs from under construction in April 2024 to operational and expanding on 10 June 2025. The money on record is CN¥220bn as of May 2025, the announced investment. Power comes from 配套200万千瓦风光绿电基地 through a renewable power purchase agreement (reported, unconfirmed). Cooling uses air cooling, with a design PUE of 1.19.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 9 public sources for this project, the latest dated 6 July 2026, and last checked the record on 14 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

A domestic 10,000-card accelerator cluster was lit in the N01 room in Aug 2024. Immersion liquid-cooled servers are in operation (Jiemian photo of 20 Apr 2026). B01 racks are 12 to 42kW.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Phases

N01 prefabricated intelligent computing building · OperationalSize not published, target 2024
N02 steel-frame building · OperationalSize not published, target 2024
B01, largest single building in the park, 30MW total IT power · Operational30 MW, target 2025
Remaining buildings of 7 planned (one due end Aug 2026, one due Dec 2026) · Under constructionSize not published, target 2026

Stage history

2024-04Under construction · gs.cnr.cn
2024-12Operational · gs.cnr.cn
2025-06-10Expanding · gansu.gansudaily.com.cn

Who is behind it

OperatorChina Mobile Gansu (中国移动通信集团甘肃有限公司) · Telco

Who uses the compute

Runs compute here · enterpriseMeitu · reported, unconfirmed

as of 2026-05-15

Press states the first intelligent computing building provides compute to Meitu and Infinigence AI, and that Capital Online and Meitu were served from August 2024.

Source · “Token工厂”,为何是甘肃庆阳? (中国电子报, 2026-05-15)

Runs compute here · GPU cloudInfinigence AI (无问芯穹) · reported, unconfirmed

as of 2026-05-15

Named as served by the park's first intelligent computing building.

Source · “Token工厂”,为何是甘肃庆阳? (中国电子报, 2026-05-15)

Tenant · GPU cloudCapital Online (首都在线) · reported, unconfirmed

as of 2025-05-14

CNR says Capital Online has been served at the China Mobile campus since August 2024. Chinanews says China Mobile's arrival brought in Kingsoft Cloud and Capital Online.

Source · 【移动数智化的甘肃拼图①】聚力“AI+”设施升级,挺进数智化“江湖” (央广网, 2025-05-14)

Tenant · hyperscalerKingsoft Cloud (金山云) · reported, unconfirmed

as of 2026-08-02

Named by China Mobile as a partner it brought to Qingyang. Kingsoft Cloud's northwest public cloud node servers are racked in the park. The building is not named.

Source · 甘肃庆阳:黄土塬上长出“数字麦田” 算力引力场聚产业生态 (中国新闻网, 2026-08-02)

Tenant · hyperscalerAlibaba · rumoured

as of 2026-04

China Mobile lists Alibaba among more than 70 partners it brought to Qingyang. This is a partner list and does not state tenancy in a China Mobile building.

Source · 东数西算看庆阳:中国移动的“算力答卷” (界面新闻, 2026-04)

Runs compute here · AI labMiniMax · rumoured

as of 2026-04

Named in the same China Mobile partner list. Tenancy in this building is not stated.

Source · 东数西算看庆阳:中国移动的“算力答卷” (界面新闻, 2026-04)

Runs compute here · AI labMoonshot AI (Kimi) · rumoured

as of 2026-04

Kimi is named in the China Mobile partner list. A separate sentence says some Moonshot AI and Zhipu training jobs have moved to Qingyang, with no building named.

Source · 东数西算看庆阳:中国移动的“算力答卷” (界面新闻, 2026-04)

Runs compute here · GPU cloudGansu Yisuan (甘肃亿算, Yitian Intelligent subsidiary) · reported, unconfirmed

as of 2025-03-19

China Mobile, Yisuan and Enflame lit Qingyang's first domestic 10,000-card cluster in the N01 room. Enflame is the chip vendor and is not recorded as a client.

Source · 甘肃庆阳:数字动能加快培育新质生产力 (科技日报, 2025-03-19)

Money at this site

Announced investment, 2025-05CN¥220bn

The figure covers the whole campus.

Colocation price per kW of IT load per month

No colocation price applies to this product (retail interconnection, no colocation price applies).

Project team
Main contractor中建三局集团有限公司 · May 2024 Confirmed source ↗
Builder of the 新型工业化绿色智算中心 building within the China Mobile (Gansu Qingyang) DC park: one building of about 488 racks plus utility tunnel, outdoor pool and pump house, and oil tank foundations. This is one sub-project, not the whole park.
Land
Industrial estate庆阳“东数西算”产业园区 · 93,333 sqm · Jun 2026 Reported source ↗
3 five-storey + 3 prefabricated DC buildings, 3 power centres, 2 substations Source states 140 mu; converted at 666.7 sqm per mu.
Power supply
Renewable power deal配套200万千瓦风光绿电基地 · Apr 2026 Reported source ↗
Matched generation of 2000MW, not data centre load. First national 绿电聚合直连供电方案; green share >80%; delivered tariff 0.398 yuan/kWh; 2 on-site substations (QQ 2026-06-20) · 2000MW is the matched wind/solar base, not DC load · Applies to the whole campus.
Water and cooling
CoolingAir cooled · design PUE 1.193 Reported source ↗
Magnetic-levitation chillers/air conditioning (磁悬浮空调) plus power modules

Sources checked 2026-10-14

  1. 【移动数智化的甘肃拼图①】聚力“AI+”设施升级,挺进数智化“江湖” (央广网, 2025-05-14)
  2. “东数西算”庆阳产业园最大单体数据中心封顶 今年9月底将整体投产交付 (甘肃日报, 2025-06-11)
  3. 算电协同:走进“庆阳样本” (通信产业报, 2026-06-20)
  4. “Token工厂”,为何是甘肃庆阳? (中国电子报, 2026-05-15)
  5. 一线调研看发展 | “瓦特”驱动“比特”——央企有效投资激活西部发展新动能 (中国证券报, 2026-04-29)
  6. 甘肃庆阳:黄土高原上跃动的绿色符号 (中国能源报, 2026-07-06)
  7. 数据基础设施加快落地 全国一体化算力网建设提速 (证券日报, 2024-07-24)
  8. 竞速数字经济新赛道 绘就“中国算谷”新蓝图——庆阳市加快建设“东数西算”国家数据中心集群 (澎湃号·政务, 2024-08-09)
  9. 中建三局承建的中国移动(甘肃·庆阳)数据中心新型工业化绿色智算中心项目开工 (中国建筑集团, 2024-05-21)

More in Qingyang

Also run by China Mobile

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.