China · China · dataset updated 2026-10-18

ArusGrid tracks 8 active data center projects in Qingyang, China, with 395 MW of planned IT load. Of these, 3 are operational and expanding, 4 are under construction and 1 is announced only.

The largest project is China Mobile (Gansu Qingyang) Data Center at 200 MW, operational and expanding. The operators with the most planned capacity here are China Mobile (200 MW across 1 project), China Telecom (135 MW across 1 project) and China Energy Engineering (60 MW across 1 project). No third party publishes a colocation vacancy rate for Qingyang, and ArusGrid does not estimate one.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.
Open the mapPipeline view

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
China Mobile (Gansu Qingyang) Data CenterQingyangExpanding200undisclosedChina Mobile Gansu (中国移动通信集团甘肃有限公司)Confirmed
China Telecom Qingyang Computing CenterQingyangExpanding135 *undisclosedChina Telecom Qingyang Branch (中国电信股份有限公司庆阳分公司)Confirmed
China Energy Engineering Qingyang Big Data Center Industrial ParkQingyangExpanding60undisclosedChina Energy Engineering (中国能源建设股份有限公司)Confirmed
China Unicom Qingyang Intelligent Computing CenterQingyangUnder construction8,000 racks *undisclosedChina Unicom (中国联通)Likely
Chindata Qingyang Zero-Carbon Data Centre Industrial Base (秦淮数据零碳数据中心产业基地)Qingyang (East Data West Computing industrial park)Under construction3,800 racks *undisclosedChindata Group (秦淮数据)No signal either way
Northwest Zero-Carbon Smart Cloud Intelligent Computing Center Phase 1QingyangUnder construction31,680 racks *undisclosedChaosuan Digital Technology (Gansu) (超算数字科技(甘肃)有限公司)Likely
Smart Blueprint Western Intelligent Computing CenterQingyangUnder construction11,075 racks *undisclosedZhichuang Lantu Digital Technology (Gansu) (智创蓝图数字科技(甘肃)有限公司)Likely
Suihong Qingyang Green Intelligent Digital Infrastructure Project (燧弘庆阳绿色智能数字基础设施项目)Qingyang (East Data West Computing industrial park)Announced2,500 racks *undisclosedGansu Suihong Green Computing (甘肃燧弘绿色算力有限公司), subsidiary of Xiamen Hongxin Electronics (300657.SZ)Likely

Other markets in China

Operators here with their own page

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. This page is generated from the dataset, so it cannot drift from the map.