China Telecom Greater Bay Area Integrated Data Centre (Shaoguan)

Shaoguan, Guangdong, China · Shaoguan market · location approximate to district level

China Telecom Greater Bay Area Integrated Data Centre (Shaoguan) is a data center project in Shaoguan, China, operated by China Telecom Guangdong (中国电信广东公司). It is operational and expanding. The operator has not published an IT load figure. It is planned for 50,400 racks. ArusGrid does not convert racks into MW.

Latest change on record: moved to expanding on 12 June 2026. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
China Telecom Guangdong (中国电信广东公司)
Telco
AI workloads
Confirmed
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Shaoguan holds 11 active projects with 200 MW of planned IT load between them, and China Telecom Greater Bay Area Integrated Data Centre (Shaoguan) has no published figure so it sits outside that ranking. Of those, 4 are operational, 1 is operational and expanding, 3 are under construction, 1 is being commissioned and 2 are announced only. No third party publishes a colocation vacancy rate for Shaoguan, and ArusGrid does not estimate one.

China Telecom has 12 others in China tracked by ArusGrid, including China Telecom Smart Cloud Base, Huailai Park (中国电信智云基地怀来园区), China Telecom Smart Cloud Base, Zhangbei Park (中国电信智慧云基地张北园区) and China Telecom Qingyang Computing Center. It sits on the Shaoguan Zhenjiang Industrial Park (韶关浈江产业园) alongside Tencent Greater Bay Area (Shaoguan) Intelligent Computing Centre. The named user of the compute is Alibaba Cloud (reported, unconfirmed).

The build is phased. Phase 1 (A1 data centre, A2 liquid-cooled AI centre) is operational with a 2024 target; Phase 2 is under construction; Phase 3 and Shaotang is announced. The dated record runs from under construction on 6 May 2023 to operational and expanding on 12 June 2026. The money on record is CN¥3.2bn as of May 2023, the announced investment. Cooling uses hybrid air and liquid cooling.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 8 public sources for this project, the latest dated 10 July 2026, and last checked the record on 19 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

Building A2 is a fully liquid-cooled intelligent computing centre (May 2024). The Zhenwu 10,000-card AI cluster went live here on 3 Apr 2026.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Phases

Phase 1 (A1 data centre, A2 liquid-cooled AI centre) · OperationalSize not published, target 2024
Phase 2 · Under constructionSize not published
Phase 3 and Shaotang · AnnouncedSize not published

Stage history

2023-05-06Under construction · gd.gov.cn
2024-05-22Operational · cagd.gov.cn
2026-06-12Expanding · stdaily.com

Who is behind it

OperatorChina Telecom Guangdong (中国电信广东公司) · Telco

Who uses the compute

Runs compute here · hyperscalerAlibaba Cloud · reported, unconfirmed

Zhenwu 10,000-card AI cluster · as of 2026-04-03

Alibaba Cloud co-launched the Zhenwu 10,000-card AI cluster at the China Telecom Greater Bay Area Intelligent Computing Centre in Shaoguan on 3 Apr 2026. Described as a joint build.

Source · 粤港澳大湾区首个“真武”万卡智算集群发布活动举行 (澎湃新闻, 2026-04-03)

Money at this site

Announced investment, 2023-05CN¥3.2bn

It includes GPUs and IT hardware, so it is not comparable with building cost.

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
Site120,000 sqm · Aug 2022 Reported source ↗
Investment 32亿元 (25亿 infrastructure, 7亿 equipment); 5.04万 racks Source states 180 mu; converted at 666.7 sqm per mu.
Water and cooling
CoolingHybrid air and liquid cooling Reported source ↗
2 fully liquid-cooled intelligent computing buildings plus 2 new-generation DC buildings supporting air and liquid cooling
CoolingDirect liquid cooling Reported source ↗
The 9 July 2026 Ascend 10,000-card cluster (30 supernodes, 9,000P) uses cold-plate liquid cooling throughout (全面采用冷板式液冷散热). Build, commissioning and go-live took 90 days, and investment was about 5.5 billion yuan.

Sources checked 2026-10-19

  1. 总投资约215亿!粤港澳大湾区枢纽韶关数据中心集群起步区首批项目集中开工 (南方财经网, 2022-08-02)
  2. 中国电信粤港澳大湾区一体化数据中心一期项目开工 打造国家级智能算力中心 (广东省人民政府门户网站, 2023-05-08)
  3. 大湾区首个大规模全液冷智能算力数据中心完工 (广东网信网, 2024-05-22)
  4. 粤港澳大湾区首个“真武”万卡智算集群发布活动举行 (澎湃新闻, 2026-04-03)
  5. 第五届粤港澳大湾区(广东)算力产业大会在韶关举行 (科技日报, 2026-06-13)
  6. 总投资约215亿!粤港澳大湾区枢纽韶关数据中心集群起步区首批项目集中开工 (21世纪经济报道, 2022-08-02)
  7. 韶关焕新:老工业基地不止“玩”算力 (第一财经, 2025-02-11)
  8. 粤港澳大湾区首个国产万卡集群在韶关上线 (科技日报) (科技日报, 2026-07-10)

Same campus, Shaoguan Zhenjiang Industrial Park (韶关浈江产业园)

More in Shaoguan

Also run by China Telecom

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.