ArusGridProject
Directory › China › Shaoguan › Zhonghanyun Shaoguan Data Centre (中瀚云韶关数据中心)

Zhonghanyun Shaoguan Data Centre (中瀚云韶关数据中心)

Shaoguan, Guangdong, China · Shaoguan market · location approximate to district level

Zhonghanyun Shaoguan Data Centre (中瀚云韶关数据中心) is a data center project in Shaoguan, China, operated by Zhonghanyun Technology (中瀚云科技股份有限公司). It has been announced and has not yet reached the land or permitting stage. The operator has not published an IT load figure. It is planned for 14,000 racks. ArusGrid does not convert racks into MW.

Latest change on record: entered the record as announced on 1 August 2022. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Announced
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Zhonghanyun Technology (中瀚云科技股份有限公司)
Colocation
AI workloads
No signal either way
Evidence grade
Sourced
Will it get built?Long shot1 of 7 gates passed
✓ Land secured○ Power arranged○ Approvals granted○ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Shaoguan holds 11 active projects with 200 MW of planned IT load between them, and Zhonghanyun Shaoguan Data Centre (中瀚云韶关数据中心) has no published figure so it sits outside that ranking. Of those, 4 are operational, 1 is operational and expanding, 3 are under construction, 1 is being commissioned and 2 are announced only. No third party publishes a colocation vacancy rate for Shaoguan, and ArusGrid does not estimate one.

It is the only Zhonghanyun Technology project ArusGrid tracks. It sits on the Shaoguan Data Center Cluster start-up zone campus alongside Guangdong Cultural Big Data Centre (广东省文化大数据中心). No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The stage was recorded as announced only on 1 August 2022. The money on record is CN¥2.98bn as of August 2022, the announced investment.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 3 public sources for this project, the latest dated 13 June 2026, and last checked the record on 19 October 2026.

How well evidenced is it

One or two hard signals sit behind the announcement. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusNo signal either way

No AI tenant or GPU deployment stated in sources.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Stage history

2022-08-01Announced · sfccn.com

Who is behind it

OperatorZhonghanyun Technology (中瀚云科技股份有限公司) · Colocation

Who uses the compute

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.

Money at this site

Announced investment, 2022-08CN¥2.98bn

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
Site140 mu · Aug 2022 Reported source ↗
140亩 ≈ 93,338 sqm (converted at 666.7 sqm/mu). Counterparty not disclosed.

Sources checked 2026-10-19

  1. 总投资约215亿!粤港澳大湾区枢纽韶关数据中心集群起步区首批项目集中开工 (21世纪经济报道 (南方财经网), 2022-08-02)
  2. 总投入215亿!大湾区枢纽韶关数据中心这五大项目集中开工 (南方都市报 (南都N视频), 2022-08-02)
  3. 第五届粤港澳大湾区(广东)算力产业大会在韶关举行 (科技日报 (stdaily), 2026-06-13)

Same campus, Shaoguan Data Center Cluster start-up zone

More in Shaoguan

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.