Directory › China › Shaoguan › Tencent Greater Bay Area (Shaoguan) Intelligent Computing Centre

Tencent Greater Bay Area (Shaoguan) Intelligent Computing Centre data center

Shaoguan, Guangdong, China · Shaoguan market · location approximate to district level

Tencent Greater Bay Area (Shaoguan) Intelligent Computing Centre is a data center project in Shaoguan, China, operated by Tencent (腾讯). It is under construction. The operator has not published an IT load figure. It is planned for 30,000 racks. ArusGrid does not convert racks into MW.

Latest change on record: moved to under construction on 18 December 2024. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Tencent (腾讯)
hyperscaler
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Leaning yes4 of 7 gates passed
✓ Land secured○ Power arranged✓ Approvals granted○ Money committed○ Tenant or own use✓ Builder appointed✓ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Shaoguan holds 11 active projects with 200 MW of planned IT load between them, and Tencent Greater Bay Area (Shaoguan) Intelligent Computing Centre has no published figure so it sits outside that ranking. Of those, 4 are operational, 1 is operational and expanding, 3 are under construction, 1 is being commissioned and 2 are announced only. No third party publishes a colocation vacancy rate for Shaoguan, and ArusGrid does not estimate one.

Tencent has 5 others in China tracked by ArusGrid, including Tencent Western Cloud Computing Data Center, Tencent Gui'an Qixing Data Center and Tencent Huailai Dongyuan Cloud Data Centre (腾讯怀来东园云数据中心). It sits on the Shaoguan Zhenjiang Industrial Park (韶关浈江产业园) alongside China Telecom Greater Bay Area Integrated Data Centre (Shaoguan). No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The dated record runs from announced only on 8 May 2024 to under construction on 18 December 2024. The money on record is CN¥5bn as of December 2024, the announced investment. Cooling uses hybrid air and liquid cooling, with a design PUE of 1.24.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 7 public sources for this project, the latest dated 9 July 2026, and last checked the record on 19 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Named an intelligent computing centre with 17.36kW average rack density. Shaoguan officials (May 2026) say Tencent 10,000-card clusters are due this year.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Phases

Phase 1, about 200,000 servers · Under constructionSize not published, target 2026

Stage history

2024-05-08Announced · news.qq.com
2024-12-18Under construction · news.dayoo.com

Who is behind it

OperatorTencent (腾讯) · hyperscaler

Who uses the compute

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.

Money at this site

Announced investment, 2024-12CN¥5bn

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Project team
Fit-out contractor深圳市卓艺建设装饰工程股份有限公司 · Jul 2026 Reported source ↗
Interior fit-out (精装修) for the Tencent Shaoguan Zhenjiang computing centre. Value not stated.
Water and cooling
CoolingHybrid air and liquid cooling · design PUE 1.235 Confirmed source ↗
Indirect evaporative cooling air handlers plus fluorine-pump air conditioners. HVDC power.

Sources checked 2026-10-19

  1. 总投资50亿元!腾讯粤港澳大湾区算力中心项目落户韶关 (羊城派, 2024-05-08)
  2. 总投资50亿元 腾讯(韶关)智算中心项目开工 (广州日报大洋网, 2024-12-19)
  3. 广东省能源局发布中国移动、腾讯、华韶数据谷三大数据中心项目节能审查意见 (搜狐, 2024-11-12)
  4. 第五届粤港澳大湾区(广东)算力产业大会在韶关举行 (科技日报, 2026-06-13)
  5. 广东省能源局关于腾讯韶关浈江算力中心节能报告的审查意见 (广东省能源局, 2024-11-07)
  6. 稳坐华南“算力之城”,粤北小城刷出全国存在感 (南方财经全媒体集团 (南方财经网), 2026-05-13)
  7. 再度携手!卓艺装饰中标腾讯韶关浈江算力中心精装修工程 (深圳市卓艺建设装饰工程股份有限公司, 2026-07-09)

Same campus, Shaoguan Zhenjiang Industrial Park (韶关浈江产业园)

More in Shaoguan

Also run by Tencent

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.