Yingshuo Huanan Shugu (South China Data Valley) Intelligent Computing Centre is a data center project in Shaoguan, China, operated by Yingshuo Group with China Electronics (鹰硕集团, 中国电子). It is operational. The operator has not published an IT load figure. It is planned for 30,000 racks. ArusGrid does not convert racks into MW.
Latest change on record: moved to operational on 11 March 2024. Record last checked against its sources on 19 October 2026.
This project is built or running, so every gate counts as passed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
Shaoguan holds 11 active projects with 200 MW of planned IT load between them, and Yingshuo Huanan Shugu (South China Data Valley) Intelligent Computing Centre has no published figure so it sits outside that ranking. Of those, 4 are operational, 1 is operational and expanding, 3 are under construction, 1 is being commissioned and 2 are announced only. No third party publishes a colocation vacancy rate for Shaoguan, and ArusGrid does not estimate one.
It is the only Yingshuo Group project ArusGrid tracks. It sits on the 中电鹰硕华南数谷大数据中心 campus. The named user of the compute is 韶关市 government and public-sector systems (政务、安监、教育、医疗、环保) (reported, unconfirmed).
The dated record runs from under construction in March 2020 to operational on 11 March 2024. The money on record is CN¥2.36bn as of April 2024, the announced investment. Cooling uses hybrid air and liquid cooling, with a design PUE of 1.25.
The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 6 public sources for this project, the latest dated 13 June 2026, and last checked the record on 19 October 2026.
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Described as an intelligent computing centre with a 16,000P heterogeneous compute pool target for phase 1.
A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.
Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source
as of 2024-03-13
centre will carry Shaoguan smart-city workloads in government, safety, industry, education, healthcare and environment
Source · 总投资23.6亿元!华南数谷智算中心投入运营 (南方日报 (南方网), 2024-03-13)
The figure covers the whole campus.
No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in Shaoguan · All projects in China · All projects operational · Full directory