Zhangjiakou, Hebei, China · Huailai market · location approximate to city level

China Telecom Smart Cloud Base, Huailai Park (中国电信智云基地怀来园区) is a data center project in Zhangjiakou, China, operated by China Telecom (中国电信). It is operational and expanding. It is planned for 150 MW of IT load.

Latest change on record: entered the record as expanding on 1 April 2026. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
150 MW
Running now
Not disclosed
Operators rarely publish this
Operator
China Telecom (中国电信)
Telco
AI workloads
Likely
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Huailai holds 8 active projects with 1,294 MW of planned IT load between them, and China Telecom Smart Cloud Base, Huailai Park (中国电信智云基地怀来园区) ranks 4th by planned capacity. Of those, 2 are operational, 5 are operational and expanding and 1 is under construction. No third party publishes a colocation vacancy rate for Huailai, and ArusGrid does not estimate one.

China Telecom has 12 others in China tracked by ArusGrid, including China Telecom Smart Cloud Base, Zhangbei Park (中国电信智慧云基地张北园区), China Telecom Qingyang Computing Center and China Telecom Cloud Computing Chongqing Base (中国电信云计算重庆基地), Shuitu. It sits on the China Telecom Smart Cloud Base Huailai Park. The named user of the compute is Tianyi Cloud (天翼云, China Telecom) (reported, unconfirmed).

The build is phased. Phase 1, 2 data centres, 3,600 high-power racks is operational; Phase 2, 3,000 high-power racks is under construction. The stage was recorded as operational and expanding on 1 April 2026. The money on record is CN¥3.2bn as of August 2026, the published figure.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 3 public sources for this project, the latest dated 28 August 2026, and last checked the record on 19 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Described as one of Hebei's largest intelligent computing centres serving Tianyi Cloud AI computing (C114, Aug 2026).

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Phases

Phase 1, 2 data centres, 3,600 high-power racks · OperationalSize not published
Phase 2, 3,000 high-power racks · Under constructionSize not published

Stage history

2026-04-01Expanding · finance.sina.cn

Who is behind it

OperatorChina Telecom (中国电信) · Telco

Who uses the compute

Own use · telcoTianyi Cloud (天翼云, China Telecom) · reported, unconfirmed

as of 2026-08-28

C114 says the park hosts Tianyi Cloud and Beijing-Tianjin-Hebei AI computing business.

Source · 河北三大运营商,在算力产业已有哪些布局? (C114通信网, 2026-08-28)

Money at this site

Figure, 2026-08CN¥3.2bn

The figure covers the whole campus.

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Project team
Design and build contractor广东省电信规划设计院有限公司 with 中国建筑一局(集团)有限公司 (consortium) · Sep 2024 · bid submitted, result pending Confirmed source ↗
2024 communications power supply phase 1 EPC (design fee 11,694,500 yuan ex-tax, equipment and install at 93.5% discount coefficient), completion by 2024-12-31

Sources checked 2026-10-19

  1. 河北三大运营商,在算力产业已有哪些布局? (C114通信网, 2026-08-28)
  2. 牢记嘱托 感恩奋进·奋力谱写中国式现代化建设河北篇章|乘势而上 算力与产业双向赋能 (河北日报 (新浪财经转载), 2026-08-01)
  3. 中国电信智慧云基地怀来园区2024年通信电源配套一期工程EPC总承包项目中标候选人公示 (知了标讯 (notice by 北京诚公管理咨询有限公司), 2024-09-01)

More in Huailai

Also run by China Telecom

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.