ArusGrid tracks 31 active data center projects in Klang Valley, Malaysia, with 1,734 MW of planned IT load. Of these, 5 are operational, 5 are operational and expanding, 10 are under construction, 6 are at the land and permitting stage and 5 are announced only. Projects under construction or commissioning account for 1,053 MW and operational sites for 215 MW of planned capacity. Operators have disclosed 82 MW actually running, a figure most of them do not publish.
The largest project is Vantage KUL2 at 436 MW, under construction. The operators with the most planned capacity here are Vantage Data Centers (467 MW across 2 projects), Vena Nexus (350 MW across 1 project) and EdgeConneX (286 MW across 3 projects). No third party publishes a colocation vacancy rate for Klang Valley, and ArusGrid does not estimate one.
Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”.
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| Vantage KUL2 | Cyberjaya | Under construction | 436 | undisclosed | Vantage Data Centers | Likely |
| Nexus Yang Green Data Centre Campus | Senawang (Seremban) | Under construction | 350 | undisclosed | Vena Nexus (Vena Group) | Likely |
| AIMS Cyberjaya AI Data Centre (200MW) | Cyberjaya | Land and permitting | 200 | undisclosed | AIMS Data Centre (TIME dotCom) | Confirmed |
| EdgeConneX Cyberjaya Campus | Cyberjaya | Under construction | 200 | undisclosed | EdgeConneX | Likely |
| Digital Cosmos Cyberjaya | Cyberjaya | Land and permitting | 182 * | undisclosed | Digital Cosmos | Likely |
| Bridge Data Centres MY01/MY02 | Cyberjaya | Expanding | 107 | 20 | Bridge Data Centres (Chindata) | Unlikely |
| EdgeConneX Bukit Jalil | Bukit Jalil | Under construction | 67 | undisclosed | EdgeConneX | No signal either way |
| MRCB / Perintis Akal AI Data Centre (Bukit Jalil) | Bukit Jalil | Announced | 65 | undisclosed | Perintis Akal Sdn Bhd (PEMANDU Partners International) | Likely |
| NEXTDC KL1 | Petaling Jaya | Expanding | 65 | 15 | NEXTDC | Likely |
| Vantage KUL1 | Cyberjaya | Operational | 31 | 31 | Vantage Data Centers | No signal either way |
| EdgeConneX KL CBD | Kuala Lumpur | Announced | 19 | undisclosed | EdgeConneX | No signal either way |
| Infinaxis CDC1 | Cyberjaya | Operational | 12 | undisclosed | Infinaxis (Gaw Capital / A3 Capital JV) | Confirmed |
| AIMS Cyberjaya (Blocks 1-3) | Cyberjaya | Expanding | none published | undisclosed | AIMS Data Centre (TIME dotCom) | No signal either way |
| AWS Asia Pacific (Malaysia) Region (3 AZs, Klang Valley) | Cyberjaya / Bukit Jalil (TPM) | Expanding | none published | undisclosed | Amazon Web Services | Likely |
| Bridge Data Centres Banting | Banting (Kota Seri Langat) | Land and permitting | none published | undisclosed | Bridge Data Centres (Malaysia VII) | No signal either way |
| Bridge Data Centres MY03 | Bukit Jalil | Expanding | none published | 16 | Bridge Data Centres (Chindata) | No signal either way |
| DayOne Kapar Campus (land assembly) | Kapar, Klang | Land and permitting | none published | undisclosed | DayOne Data Centers (ex-GDS International) | Likely |
| DayOne Southville City Campus (ex-Mah Sing DC Hub) | Bangi | Land and permitting | none published | undisclosed | DayOne Data Centers (ex-GDS International) | Likely |
| Equinix KL2 | Cyberjaya | Announced | none published | undisclosed | Equinix | Confirmed |
| Exsim Sri Permaisuri Data Centre (Cheras) | Bandar Sri Permaisuri (Cheras) | Under construction | none published | undisclosed | Exsim Sri Permai Sdn Bhd (Exsim Group) | No signal either way |
| Global Data Infrastructure Kota Seri Langat | Banting | Announced | none published | undisclosed | Global Data Infrastructure (Global Telecommunications Group) | No signal either way |
| Google (Pearl Computing) Elmina Data Centre & Cloud Region | City of Elmina, Shah Alam | Under construction | none published | undisclosed | Google (via Pearl Computing) | Likely |
| Google (Pearl Computing) Port Dickson | Port Dickson (Bandar Springhill) | Under construction | none published | undisclosed | Google (Pearl Computing Malaysia) | Likely |
| Google (Pearl Computing) Puncak Alam | Puncak Alam | Under construction | none published | undisclosed | Google (Pearl Computing Malaysia) | Likely |
| Google (reported) Serendah Campus | Serendah (Hulu Selangor) | Land and permitting | none published | undisclosed | Pearl Computing (Google), attribution reported | Likely |
| Google Elmina 2 (SDP EBP Asset II) | Sungai Buloh (City of Elmina) | Under construction | none published | undisclosed | Google (Pearl Computing Malaysia) | Likely |
| Microsoft Malaysia West Region (3 sites, Greater KL) | Greater Kuala Lumpur | Operational | none published | undisclosed | Microsoft | Likely |
| NTT GDC Cyberjaya Campus (CBJ1-CBJ6) | Cyberjaya | Operational | none published | undisclosed | NTT Global Data Centers | No signal either way |
| Regal Orion Shinsei 1 | Labu (Bandar Enstek) | Under construction | none published | undisclosed | Regal Orion Sdn Bhd | No signal either way |
| TM One Klang Valley Core Data Centre (KVDC) | Cyberjaya | Operational | none published | undisclosed | TM One (Telekom Malaysia) | Unlikely |
| Tera Data Centers Port Dickson (Eco Business Park 7) | Port Dickson (Mukim Jimah) | Announced | none published | undisclosed | Tera Data Centers (Malaysia) Sdn Bhd | Likely |