How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsNo
AI workloads
StatusLikely
AI-ready marketing; first Uptime Tier IV cert in Peninsular MY; 2026 greenfield by listed AU operator
Phases
Phase 1 · Operational15 MW, target 2026
Phases 2-5 · Announced50 MW
Who is behind it
OperatorNEXTDC · Colocation
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Money at this site
Announced investment, 2026-05A$1,000m (about US$650m)
Who builds it
Main contractorPembinaan Mitrajaya Sdn Bhd · RM375.5m (≈US$85m) · Jan 2025 Reported source ↗ KL1 main works: Stage 1 Ph2, Stage 2, Stage 3 Ph1 (original award)
Main contractorPembinaan Mitrajaya Sdn Bhd · RM426.3m (≈US$96m) · Sep 2025 Reported source ↗ KL1 variation orders adding later phases; contract to RM801.8m, complete Apr 2026
Main contractorPembinaan Mitrajaya Sdn Bhd · RM42.81m (≈US$10m) · Jan 2026 Reported source ↗ Fourth VO, Phase 3 Stage 1; contract to RM844.66m, complete Jul 2026
Piling and earthworksPembinaan Mitrajaya Sdn Bhd · RM54m (≈US$12m) · Mar 2026 Reported source ↗ KL1 Stage 4 early works (ST4-GC01), to Oct 2026