How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsNo
AI workloads
StatusNo signal either way
no cooling/density/tenant signal published
Phases
Initial · Under construction22 MW, target 2026
Full build · Announced67 MW
Who is behind it
OperatorEdgeConneX · Colocation
Funder, EquityEQT
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Platform deals that include it
EdgeConneX Malaysia program
Country programme, 2023-09US$2.0bn
Platform capital spans several sites. It is never added to this project's own figure.
Power supply
Dedicated substation132kV · Mar 2026 Confirmed source ↗ 132kV substation; 22.4MW growing to 67MW · Applies to the whole campus.
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedJati Tinggi Holding Sdn Bhd · Grid and substation works · RM6.59m (≈US$2m) · Sep 2024 source ↗ This project is one of 3 that fit. The others are Bridge Data Centres MY03, MRCB / Perintis Akal AI Data Centre (Bukit Jalil).