EdgeConneX Cyberjaya Campus

Cyberjaya, Selangor, Malaysia · Klang Valley market · location approximate to city level

EdgeConneX Cyberjaya Campus is a data center project in Cyberjaya, Malaysia, operated by EdgeConneX. It is under construction. It is planned for 200 MW of IT load.

Latest change on record: entered the record as under construction on 15 July 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
200 MW
Running now
Not disclosed
Operator
EdgeConneX
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed○ Tenant or own use✓ Builder appointed✓ Construction started

Next gate to watch: Tenant or own use.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. On record: named funder, dated, sized phase, three or more sources, dated source in the last 24 months. Criteria.

AI workloads

StatusLikely

200MW modern campus plan

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.

Phases

First building · Under construction22 MW, target 2027

Stage history

2026-07-15Under construction · techwireasia.com

Who is behind it

OperatorEdgeConneX · Colocation
Funder, EquityEQT

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

ArusGrid estimate, building costabout US$1.9bn to US$2.9bn

No figure has been announced. This range is 200 MW of planned IT load times a published benchmark of US$11.37 per watt for Malaysia, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Platform deals that include it

EdgeConneX Malaysia program
Country programme, 2023-09
US$2.0bn

Platform capital spans several sites. It is never added to this project's own figure.

Project team
Main contractorBCEI · Jan 2025 Inferred by ArusGrid source ↗
Construction of the EdgeConneX Kuala Lumpur (Cyberjaya) data centre project. EdgeConneX credits BCEI for 1.5 million safe work hours on the project.
Why we think so. EdgeConneX's own blog names BCEI as the partner behind the 1.5 million safe work hours at the Cyberjaya project. It does not state BCEI's role. Main contractor is our reading because BCEI is described elsewhere as a firm that plans, designs and builds IT facilities.
Land
Industrial estateCyberview Sdn Bhd · 30 acres · Sep 2023 Reported source ↗
Nine buildings over 30 acres. Deal finalised with Cyberview, nature of transaction not stated.
Land sellerCyberview Sdn Bhd · 30 acres · Sep 2023 Reported source ↗
EdgeConneX signed a Sales and Purchase Agreement with Cyberview for an enterprise lot of roughly 30 acres. The source does not say whether the title is freehold or leasehold.
Power supply
Dedicated substation275kV · Mar 2026 Confirmed source ↗
275kV substation; 22.4MW growing to 200MW · Applies to the whole campus.
Water and cooling
CoolingClosed-loop cooling Reported source ↗
Closed-loop non-evaporative, air heat rejection; ~9 million litres/day saved vs water-cooled
Cooling Confirmed source ↗
N+1 chilled water system with N+1 fan wall units or CRAHs in separate suites. The data sheet covers all three EdgeConneX Kuala Lumpur sites (CBD, Cyberjaya, Bukit Jalil), not Cyberjaya alone.
Cooling Confirmed source ↗
EdgeConneX's Kuala Lumpur data sheet (Q1 2026 update) lists an N+1 chilled water system with N+1 fan wall units or CRAHs in separate suites, and cabinets capable of 20kW. The sheet covers the CBD, Cyberjaya and Bukit Jalil sites together and does not say whether the chillers are air or water cooled.
CoolingClosed-loop cooling Reported source ↗
Non-evaporative, closed-loop heat rejection through air with high-efficiency chillers, used whether halls are air or liquid cooled at the rack.
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedSunway Construction Sdn Bhd · Main contractor · RM747.8m (≈US$168m) · Mar 2024 source ↗
This project is one of 4 that fit. The others are Google (Pearl Computing) Elmina Data Centre & Cloud Region, AWS Asia Pacific (Malaysia) Region (3 AZs, Klang Valley), Vantage KUL2.
UnconfirmedGamuda Engineering Sdn Bhd · Civil and structural works · RM451.4m (≈US$102m) · Oct 2024 source ↗
This project is one of 2 that fit. The other is AWS Asia Pacific (Malaysia) Region (3 AZs, Klang Valley).

Sources

  1. datacenterdynamics.com
  2. edgeconnex.com
  3. Malaysia's AI data center vision: How EdgeConneX is building for the future (TechWire Asia, 2026-07-15)
  4. Cyberjaya Scales as a Regional Data Center Hub (EdgeConneX, 2026-07-01)
  5. Kuala Lumpur Data Sheet Q1 update (EdgeConneX, 2026-03)
  6. Building Safely Together: Celebrating a Major Milestone at EdgeConneX Kuala Lumpur Project (EdgeConneX, 2025-01-04)
  7. Gamuda lands RM451.4m deal to construct Cyberjaya data centre, to start in 4Q 2024, complete in 1Q 2026 (Malay Mail, 2024-11-01)
  8. EdgeConneX invests in new 200MW data centre campus in Cyberjaya (Digital News Asia, 2023-09-11)
  9. KL Malaysia (EdgeConneX)