How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusConfirmed
up to 80kW/rack design
Phases
Phase 1 · Operational12 MW, target 2026
Stage history
Who is behind it
OperatorInfinaxis (Gaw Capital / A3 Capital JV) · Joint venture
Funder, EquityGaw Capital Partners
Funder, Joint venture partnerA3 Capital
Client, reported, unconfirmedUnnamed (>80% Ph1 pre-committed)
Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from?