Google Elmina 2 (SDP EBP Asset II) is a data center project in Sungai Buloh (City of Elmina), Malaysia, operated by Google (Pearl Computing Malaysia). It is under construction. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Next gate to watch: Power arranged.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.
Construction or financing is evidenced, or several independent signals agree. On record: named funder, committed or approved capital, three or more sources, dated source in the last 24 months. Criteria.
Second Google hyperscale building at Elmina, sister to $2B first campus
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.
Full facility, 77 acres Elmina Business Park Phase 2, 20-year lease, rent up to RM5.6bn, completion target Dec 2027 · as of 2024-12-02
DCD reports Sime Darby Property's second Bursa-announced build-and-lease with Pearl Computing Malaysia Sdn Bhd (subsidiary of Raiden APAC Pte Ltd), 77 acres at Elmina Business Park Phase 2, RM5.6bn over the initial 20-year term, and calls Pearl 'Google-affiliated'. IJM's RM874m M&E fit-out award (The Edge, 2025-10-29) names Pearl Computing as end-user at Elmina.
Source · Malaysia's Sime Darby Property leases more land to Google for second data center (DCD, 2024-12-02)
Source · IJM lands another data centre contract at Elmina Business Park, this time worth RM874m (The Edge Malaysia, 2025-10-29)
Sime Darby Property build-and-lease to Pearl Computing (Google), up to RM5.6bn over 20 years Electricity excluded. As of 2024-12. The Edge Malaysia reporting the Bursa filing, 2024-12-02
About RM280m a year. Analysts put the build at RM2.5bn to 3bn, a 9 to 11 percent gross yield on cost.
An own-use build. No colocation price applies.
All projects in Klang Valley · All projects in Malaysia · All Google projects · All projects under construction · Data center rules in Malaysia · Full directory