Who is behind it
OperatorGoogle (Pearl Computing Malaysia) · Hyperscaler self-build
Funder, Joint venture partnerEcoWorld (Quantum Alpha)
Who uses the compute
Own use · hyperscalerGoogle (Pearl Computing Malaysia Sdn Bhd) · confirmed
Full facility, 92.44 acres built and leased by Quantum Alpha Sdn Bhd (EcoWorld) at Eco Business Park V, plus 58.187 acres sold outright for RM266.1m; lease up to RM4.8bn over 20 years · as of 2025-02-25
The Edge reports EcoWorld's Bursa filing, in which Paragon Pinnacle Sdn Bhd sells 58.187 acres to Pearl Computing Malaysia Sdn Bhd and Quantum Alpha Sdn Bhd builds and leases a data centre on 92.44 acres at Eco Business Park V, with Pearl described in the filing as 'an affiliate of Google'. The landlord's filing itself ties the SPV to Google.
Source · EcoWorld to sell RM266m land, lease data centre to Google affiliate (The Edge Malaysia, 2025-02-25)
Source · Malaysia's EcoWorld sells and leases land outside Kuala Lumpur to Google for data center (DCD, 2025-02-25)
Money at this site
Debt raised, 2026-01RM1,880m (about US$420m)
This is the size of a loan. ArusGrid excludes it from capital spending totals.
The figure covers the whole campus.
Project team
Core and shell builderGamuda Engineering Sdn Bhd · RM2.14bn (≈US$482m) · Aug 2025 Confirmed source ↗ Shell and core of two DC blocks, consumer substation, water reservoir; 3Q2025 to 3Q2027
Mechanical and electrical worksKee Ming Electrical Sdn Bhd · RM21.36m · Jun 2026 Inferred by ArusGrid source ↗ Supply and installation of HV, MV, LV and ELV external utilities, telecom duct works and main building electrical works for a hyperscale data centre in Puncak Alam, awarded by an unnamed M&E contractor. Completion due 30 Dec 2026.
Why we think so. The filing gives a hyperscale data centre in Puncak Alam, Selangor, under an unnamed M&E contractor. Google's Pearl Computing campus (EcoWorld EBP V, Gamuda main contractor) is the only Puncak Alam data centre in our index and is under construction with the same timing.
Mechanical and electrical worksSJEE Engineering Sdn Bhd · RM105m (≈US$24m) · Aug 2026 Inferred by ArusGrid source ↗ Electrical Package #3 (MV02 and MV03), subcontract; 2026-07-21 to 2027-10-14
Why we think so. Puncak Alam hyperscale DC under a local main contractor; our only Puncak Alam project is Google's EBP V build where Gamuda is main contractor.
Mechanical and electrical worksKee Ming Group Bhd · RM44.17m · Nov 2026 Inferred by ArusGrid source ↗ Electrical engineering subcontract (general electrical and main building electrical works) for a hyperscale data centre in Puncak Alam, awarded by an unnamed M&E contractor. Works to finish by 30 Jul 2027. Second award from the same development after the June 2026 RM21.36m package.
BidderSunway Construction Group Bhd · Jul 2025 · bid submitted, result pending Reported source ↗ Tipped contender for EcoWorld EBP V core and shell (Pearl Computing); Gamuda later won
Land
Land sellerEco World Development Group Bhd (Paragon Pinnacle Sdn Bhd / Quantum Alpha Sdn Bhd) · 58.187 acres · RM266.1m (≈US$60m) · Feb 2025 Confirmed source ↗ Eco Business Park V; buyer Pearl Computing Malaysia Sdn Bhd
LandlordEco World Development Group Bhd (Quantum Alpha Sdn Bhd) · 92.44 acres · RM4.8bn (≈US$1.1bn) · leased · Feb 2025 Confirmed source ↗ Build-and-lease of shell and core to Pearl Computing; 20yr + 2x5yr options; est. total rent RM4.8bn; completion Oct 2027
Power supply
Renewable power dealNot named (solar projects in Malaysia) · 50 MW · 2025 Confirmed source ↗ Google's 2026 Environmental Report says it signed its first solar deals in Malaysia for approximately 50 MW. The report does not name a site or counterparty. · Country portfolio deal, not tied to Puncak Alam. · Covers the operator's wider portfolio in this country, not this site alone.
Power allocation or planTenaga Nasional Berhad (strategic collaboration with Google) · 1,000 MW · Nov 2026 Reported source ↗ Google says the investment will add more than 1GW of clean energy capacity to Malaysia's grid. New clean generation will be developed under Malaysia's Corporate Renewable Energy Supply Scheme (CRESS) through a collaboration with TNB, which will also explore round-the-clock clean energy projects. · Platform commitment covering Google's Malaysia campuses, not Puncak Alam alone. The 1GW is generation capacity, not data centre load. W.Media adds that Google will pay for all of the power its campuses use and the direct grid connection costs. · Covers the operator's wider portfolio in this country, not this site alone.
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedTRC Construction Sdn Bhd · Utility infrastructure · RM149.98m (≈US$34m) · Aug 2026 source ↗ This project is one of 2 that fit. The other is Google (Pearl Computing) Port Dickson.
UnconfirmedSJEE Engineering Sdn Bhd · Mechanical and electrical works · RM146.53m (≈US$33m) · Aug 2026 source ↗ This project is one of 2 that fit. The other is Google Elmina 2 (SDP EBP Asset II).