ArusGridOperator
Directory › Operators › Vantage Data Centers

Vantage Data Centers data center projects

Malaysia · dataset updated 2026-09-27

ArusGrid tracks 3 active data center projects operated by Vantage Data Centers, with 767 MW of planned IT load, across Malaysia. Of these, 1 is operational, 1 is operational and expanding and 1 is under construction. Projects under construction or commissioning account for 436 MW. Disclosed running capacity is 56 MW.

ArusGrid classes the operator as colocation. Projects appear under the names Vantage Data Centers (acquired from Yondr Group). The largest project is Vantage KUL2 at 436 MW in Klang Valley, under construction. AI workloads are confirmed at 1 site. Named funders across its projects are DigitalBridge, GIC and ADIA. No tenant is disclosed at any of its projects, which is normal for colocation and says nothing about occupancy.

Open the mapRelationship graph

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
Vantage KUL2CyberjayaUnder construction436undisclosedVantage Data CentersLikely
Vantage JHB1 (ex-Yondr)Sedenak (Kulai)Expanding30025Vantage Data Centers (acquired from Yondr Group)Confirmed
Vantage KUL1CyberjayaOperational3131Vantage Data CentersNo signal either way

Markets where it builds

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.