ArusGrid tracks 10 active data center projects in the Philippines with 529 MW of planned IT load, spread over 2 markets. Of these, 7 are operational, 1 is at the land and permitting stage, 1 is announced only and 1 is on hold. Disclosed running capacity is 78 MW.
Greater Manila is the largest market with 9 projects and 517 MW planned. The operators with the most planned capacity in the country are VITRO (ePLDT) (150 MW), STT GDC (124 MW), Evolution DC (100 MW), Digital Halo (70 MW) and A-FLOW (36 MW).
Grid power for a large industrial user in the Philippines costs about US$0.12 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in the Philippines, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”.
| Market | Projects | Planned MW | Under construction MW | Operational MW | Colocation vacancy |
|---|---|---|---|---|---|
| Greater Manila | 9 | 517 | 0 | 312 | 43.6% (June 2026) |
| Clark / Central Luzon | 1 | 12 | 0 | 12 | not published |
Vacancy is the share of built, leasable colocation capacity sitting empty, as published by a third party. It excludes hyperscaler self-build and is never estimated.
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| STT Fairview (STT GDC 'Polaris' campus) | Quezon City | Operational | 124 | 32 | STT GDC Philippines | Likely |
| Evolution PH01 Manila (Gateway Business Park, General Trias) | General Trias | Land and permitting | 100 | undisclosed | Evolution Data Centres | Likely |
| VITRO General Trias (PLDT 12th data center) | General Trias | Announced | 100 | undisclosed | VITRO Inc. (ePLDT / PLDT) | Likely |
| Digital Halo MNL1 | Cainta | Operational | 70 | 6.5 | Digital Halo | Likely |
| VITRO Sta. Rosa (VSR) | Santa Rosa | Operational | 50 | 10 | VITRO Inc. (ePLDT / PLDT) | Confirmed |
| A-FLOW ML1 | Biñan | Operational | 36 | 6 | A-FLOW (FLOW Digital Infrastructure x AyalaLand Logistics) | No signal either way |
| The Hive (Beeinfotech PH) | Quezon City (Bridgetowne) | Operational | 20 | undisclosed | Bee Information Technology PH (Beeinfotech) | Likely |
| Converge Angeles Data Center | Angeles City | Operational | 12 | 12 | Converge ICT Solutions | Likely |
| YCO Cloud Campus One (Malvar One / M1) | Malvar | Operational | 12 | 12 | YCO Cloud Centers | No signal either way |
| EdgeConneX / Aboitiz InfraCapital MNL01 | Metro Manila (site not disclosed) | On hold | 5 | undisclosed | EdgeConneX / Aboitiz InfraCapital JV | No signal either way |
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| Narra Technology Park hyperscale campus | Capas / Bamban (New Clark City) | Cancelled | 300 | undisclosed | Endec Group / Narra Technology Park Development Inc. | No signal either way |
| Converge Parañaque hyperscale data center | Parañaque | Cancelled | 49 | undisclosed | Converge ICT Solutions | No signal either way |
VITRO (ePLDT) · STT GDC · Evolution DC · Digital Halo · Converge ICT · EdgeConneX