How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsNo
AI workloads
StatusNo signal either way
No public signal either way.
Phases
ML1 Phase 1 · Operational6 MW, target 2025
ML2 / ML3 · Announced30 MW
Who is behind it
OperatorA-FLOW (FLOW Digital Infrastructure x AyalaLand Logistics) · Joint venture
Funder, Joint venture partnerFLOW Digital Infrastructure
Funder, Joint venture partnerAyalaLand Logistics Holdings Corp.
Funder, DebtLand Bank of the Philippines
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Money at this site
Debt raised, 2024-07PHP 10.8bn (about US$190m)
This is the size of a loan. ArusGrid excludes it from capital spending totals.
The figure covers the whole campus.
Who builds it
Main contractorMonocrete Construction Philippines · completed Confirmed source ↗ ML1 building construction, topped off Sep 2024
Land
LandlordA-FLOW Land I Corp (60% AyalaLand Logistics Holdings) · 5 ha · leased · Apr 2026 Confirmed source ↗ A-FLOW Land I Corp holds title to a 5 ha property in Mamplasan, Binan, leased to A-FLOW I Properties Corp for the data center.
Power supply
Dedicated substationMeralco · 115kV · Aug 2024 Confirmed source ↗ Switching Station Agreement and Deed of Usufruct signed for a dedicated 115kV switching station with dual feed. Target completion December 2025.