Converge Angeles Data Center

Angeles City, Pampanga, Philippines · Clark / Central Luzon market · location approximate to city level

Converge Angeles Data Center is a data center project in Angeles City, Philippines, operated by Converge ICT Solutions. It is operational. It is planned for 12 MW of IT load. The operator reports 12 MW running.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
12 MW
Running now
12 MW
Operators rarely publish this
Operator
Converge ICT Solutions
Telco
AI workloads
Likely
Evidence grade
Verified

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Opened Mar 2026 as a 'scalable AI-ready facility' hosting Converge Cloud, Converge's sovereign-cloud offering aimed at AI startups (BusinessWorld/Inquirer/StartupNewsPH, Mar 2026). Stated AI purpose = 'likely'. No cooling spec or GPU count published.

Phases

Installed capacity · Operational12 MW, target 2026

Who is behind it

OperatorConverge ICT Solutions · Telco
Funder, EquityConverge ICT Solutions

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Announced investment, 2026-03PHP 5bn (about US$87m)

Platform deals that include it

Converge ICT 2026 capex guidance
Other
US$400m

Platform capital spans several sites. It is never added to this project's own figure.

Power supply
Renewable power dealGreencore Geothermal (First Gen) · 7.2 MW · Apr 2022 Inferred by ArusGrid source ↗
Geothermal supply under a retail competition and open access contract. · Two-year retail supply contract to 2024, reported as 14.4MW in total or 7.2MW a year. Renewal not confirmed.
Why we think so. Converge's Pampanga data centre run by ComClark; our only Converge project in Pampanga is the Angeles City facility.

Sources checked 2026-09-26

  1. bworldonline.com
  2. business.inquirer.net
  3. datacenterdynamics.com
  4. startupnews.ph
  5. Converge accelerates enterprise growth engine as Angeles Data Center secures national strategic investment status (Converge ICT, 2026-08-27)
  6. Converge data center gets 'green lane' tag (Inquirer, 2026-08-28)
Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-26.