How well evidenced is it
Running capacity. The site is operational or expanding. On record: named funder, disclosed client (confirmed), dated, sized phase, three or more sources, dated source in the last 24 months. Criteria.
AI workloads
StatusLikely
Operator describes hyperscale, high power density design on a 300MW-plus campus.
Access to AI chips
GradeNo US licence required
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.
Phases
BOM1 phase 1 · Operational15 MW, target 2026
Stage history
Who is behind it
OperatorDigital Edge DC · Colocation
Funder, EquityStonepeak
Funder, Joint venture partnerNational Investment and Infrastructure Fund (NIIF)
Funder, Joint venture partnerAGP DC InvestCo
Who uses the compute
Tenant · hyperscalerUndisclosed hyperscaler (Indian affiliate, anchor customer) · confirmed
Anchor customer for BOM2. The loan security covers the Anchor Customer Contract with the Indian affiliate of a hyperscaler that has entered or will enter into it. The hyperscaler is not named. · as of 2026-01-16
Company EGM notice for the SBI BOM2 loan names the anchor customer as the Indian affiliate of a hyperscaler. ICRA (held) says BOM1 and BOM2 are contracted to one unnamed customer.
Source · Notice of 06/2025-26 Extra-Ordinary General Meeting (EGM) of the Members of Digital Edge DC (India) Private Limited (Digital Edge DC (India) Private Limited, 2026-02-19)
Money at this site
Estimate, 2024-03INR 13.95bn (about US$168m)
This figure is an estimate. ArusGrid excludes it from totals.
Platform deals that include it
Digital Edge 83MW solar PPA with Hexa Climate for Navi Mumbai phase 1
Power deal, 2026-02Not disclosed
Platform capital spans several sites. It is never added to this project's own figure.
Colocation price per kW of IT load per month
ArusGrid estimate, grade CINR 6,800 to INR 8,900 (about USD 81 to 106)
ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.
Land
Land sellerAssetz Property Group (land originally held by Mukand Ltd) · 47 acres · INR 806m · Jan 2023 Reported source ↗ Reported as advanced talks (ET via DCD/W.Media); parcel spans Dighe and Kalwe, Thane-Belapur belt. DCD 2024-05-22 groundbreaking report confirms Digital Edge's Navi Mumbai campus is a 47-acre site, matching size and location. Price is 'more than Rs 806 crore'. Reported as advanced talks in January 2023; price stated as more than this figure.
Power supply
Renewable power dealHexa Climate · 83 MW · Feb 2026 Reported source ↗ Solar PPA for the first phase. · 83MW is generation contracted, not IT load.
Renewable power dealHexa Climate Solutions Pvt Ltd · 83 MW · Feb 2026 Confirmed source ↗ Up to 83MW solar, chosen by competitive tender, with Digital Edge India taking a substantial minority equity stake to secure captive user status. Phased delivery from December 2026. · May duplicate the existing power fact on this row. · Applies to the whole campus.
Renewable power dealHexa Climate Solutions Pvt Ltd · 83 MW · Feb 2026 Reported source ↗ Up to 83MW solar for first phase; supply from December 2026. · Article calls it the 350MW BOM campus (Digital Edge/NIIF/AGP JV). · Applies to the whole campus.
Power allocation or plan450.356 MW · Feb 2024 Confirmed source ↗ EC requires at least 5% of energy from solar or other renewables and a registered green PPA for at least 5%. · Connected load 450,356 kW and demand load 450,264 kW as stated in the EC. This is connected load, not IT load. Backup DG sets 1250 kVA x 65. · Applies to the whole campus.
Dedicated substationDigital Edge DC (India) own 220kV gas insulated substation (grid utility not named) · 220kV · Jan 2026 Confirmed source ↗ Members approved State Bank of India loan facilities to build the BOM2 data centre and a 220kV gas insulated substation as one project, per sanction letter PFSBU/Team-11/2025-26/DEDC/1442 dated 6 Jan 2026. The substation plot, grey water tank, sewage plant, gate house and a 6m road form the BOM2 Common Infrastructure on 9,173.23 sqm of company land. No MVA rating is given. · Applies to the whole campus.
Water and cooling
WaterRecycled wastewater · 10 MLD Confirmed source ↗ Applies to the BOM campus in Navi Mumbai. Municipal agency not named.
CoolingDirect liquid cooling · design PUE 1.25 Confirmed source ↗ Release describes market leading liquid cooling. Greywater that the municipality would otherwise discharge to the ocean is recycled for cooling.
WaterRecycled wastewater · 10 MLD Reported source ↗ Supplier not named (municipal greywater).
'advanced liquid cooling systems powered by 10 million litres of recycled water per day'; greywater otherwise discharged to sea by municipal authorities.
WaterMains drinking water · Navi Mumbai Municipal Corporation (NMMC) · 158 m³ a day Confirmed source ↗ 158 KLD total: 5 KLD fresh domestic, 8 KLD recycled flushing, 145 KLD landscape. STP 12 CMD.
EC water table covers domestic, flushing and landscape use only; no cooling water line.
WaterRecycled wastewater · 10 MLD Confirmed source ↗ Design WUE target below 1.75. Design PUE of 1.25 is already held. WUE target below 1.75.
CoolingDirect liquid cooling Confirmed source ↗ Digital Edge says liquid cooling is supplied by about 10 million litres a day of recycled greywater that the municipality would otherwise discharge to sea.