ArusGridProject
Directory › India › Mumbai metro › CtrlS Mumbai datacenter campus (DC1 to DC7)

CtrlS Mumbai datacenter campus (DC1 to DC7)

Navi Mumbai, Maharashtra, India · Mumbai metro market · location approximate to district level

CtrlS Mumbai datacenter campus (DC1 to DC7) is a data center project in Navi Mumbai, India, operated by CtrlS Datacenters. It is operational. The published capacity figure is 214 MW, and its basis is not stated as IT load. The operator reports 119 MW running.

Latest change on record: entered the record as operational on 6 February 2025. Record last checked against its sources on 17 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
214 MW
unstated
Running now
119 MW
Operators rarely publish this
Operator
CtrlS Datacenters
Colocation
AI workloads
No signal either way
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How India approves, powers and taxes data centers is on Data center rules in India.

Where it sits

Mumbai metro holds 32 active projects with 2,694 MW of planned IT load between them, and CtrlS Mumbai datacenter campus (DC1 to DC7) ranks 5th by planned capacity. Of those, 4 are operational, 5 are operational and expanding, 11 are under construction, 6 are at the land and permitting stage and 6 are announced only. Published colocation vacancy in Mumbai metro was 6.6% as of June 2025. Vacancy excludes hyperscaler self-build.

CtrlS has 4 others in India tracked by ArusGrid, including CtrlS Chandanvelly datacenter park, CtrlS Bodh Gaya AI Factory and CtrlS Chennai datacenter park (DC1 and DC2). It sits on the CtrlS Navi Mumbai campus, Electronic Zone, MIDC Mahape. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The build is phased. DC1 and DC2 at 40 MW is operational; DC3 at 10 MW is operational; DC4 at 37 MW is operational. The stage was recorded as operational on 6 February 2025. Power comes from CtrlS own gas insulated substation (grid utility not named) through a dedicated substation at 220 kV (reported, unconfirmed).

The US export control position for advanced AI chips in India, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 3 public sources for this project, the latest dated 28 July 2026, and last checked the record on 17 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusNo signal either way

No AI tenant or GPU deployment is named for this campus.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

DC1 and DC2 · Operational40 MW
DC3 · Operational10 MW
DC4 · Operational37 MW
DC5 · Operational32 MW
DC6 and DC7 · Announced95 MW

Stage history

2025-02-06Operational · datacenterdynamics.com

Who is behind it

OperatorCtrlS Datacenters · Colocation

Who uses the compute

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.

Colocation price per kW of IT load per month

ArusGrid estimate, grade CINR 6,800 to INR 8,900 (about USD 81 to 106)

ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, hyperscale (2024-12)INR 6,800 to INR 8,900 Cushman & Wakefield for Sify Infinit Spaces, 2025-10-16
Power supply
Dedicated substationCtrlS own gas insulated substation (grid utility not named) · 300 MW · 220kV · Jul 2024 Reported source ↗
Grid power at the Mumbai campus GIS was raised from 150MW to 300MW. Incoming 220kV feeders use LILO plus radial configuration. CtrlS says the substation can scale to 700MW. · Applies to the whole campus.

Sources checked 2026-10-17

  1. Rated-4 Data Center in Mumbai | CtrlS (CtrlS, 2026-07-28)
  2. CtrlS completes 125MW solar farm to power Mumbai campus (DCD, 2025-02-06)
  3. CtrlS Doubles Mumbai Data Centre Power Capacity to 300 MW (TelecomTalk, 2024-07-31)

More in Mumbai metro

Also run by CtrlS

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.