How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesNo
Dated source in the last 24 monthsYes
AI workloads
StatusLikely
Tower 5 marketed as hyperscale-ready at 43.2MW; Sify has publicised GPU cloud offerings.
Access to AI chips
GradeNo US licence required
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Phases
Towers 1 to 4 · OperationalSize not published
Tower 5 · Operational43 MW
Towers 6, 7, 11, 12 · Under constructionSize not published, target 2026
Towers 8, 9, 10 · AnnouncedSize not published
Stage history
Who is behind it
OperatorSify Infinit Spaces · Colocation
Funder, EquitySify Technologies
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Power supply
Dedicated substationon-site substations · 220kV Confirmed source ↗ Operator claims up to 70% renewable energy and 99MW of green power from solar and wind. · 110kV substation for towers 1 to 3 and 220kV GIS substation for towers 4 to 6, per operator. · Applies to the whole campus.