Colt Airoli expansion campus

Navi Mumbai (Airoli), Maharashtra, India · Mumbai metro market · location approximate to district level

Colt Airoli expansion campus is a data center project in Navi Mumbai (Airoli), India, operated by Colt Data Centre Services. It is under construction. The published capacity figure is 100 MW, and its basis is not stated as IT load.

Latest change on record: moved to under construction on 15 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
100 MW
unstated
Running now
Not disclosed
Operator
Colt Data Centre Services
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Builder appointed.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How India approves, powers and taxes data centers is on Data center rules in India.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. On record: named funder, disclosed client (confirmed), committed or approved capital, three or more sources, dated source in the last 24 months. Criteria.

AI workloads

StatusLikely

Mumbai 3 uses hybrid air and direct-to-chip liquid cooling and is leased to a hyperscaler (DCD, 2026-10-15).

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.

Phases

Phase A · Land and permitting30 MW
Mumbai 3 · Under construction64 MW

Stage history

2024-07-18Land and permitting · datacenterdynamics.com
2026-10-15Under construction · datacenterdynamics.com

Who is behind it

OperatorColt Data Centre Services · Colocation
Funder, Joint venture partnerRMZ

Who uses the compute

Tenant · hyperscalerUndisclosed hyperscaler · confirmed

64 MW · Mumbai 3 · as of 2026-10-15

DCD reports work started after Colt and RMZ secured a lease with a hyperscaler for the 64MW building.

Source · Colt DCS and RMZ start work on third facility at Mumbai campus, India (DCD, 2026-10-15)

Money at this site

Announced investment, 2024-11INR 85bn (about US$1.0bn)

The figure covers the whole campus.

Colocation price per kW of IT load per month

ArusGrid estimate, grade CINR 6,800 to INR 8,900 (about USD 81 to 106)

ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, hyperscale (2024-12)INR 6,800 to INR 8,900 Cushman & Wakefield for Sify Infinit Spaces, 2025-10-16
Land
Site15 acres · Jul 2024 Reported source ↗
Reported acquisition (people with knowledge) of parcel next to existing Airoli facility for the 100 MW (30 MW phases) build. Rs 8,500 crore is project investment, not land price. Seller not named.
Power supply
Dedicated substation64 MW · 220kV · Oct 2026 Reported source ↗
Mumbai 3 will operate on 100% renewable energy; sourcing mechanism not stated · 220kV gas-insulated substation on the Navi Mumbai campus; 64MW is secured contracted power for Mumbai 3 on completion. Utility not named.
Power allocation or planNot named · Oct 2026 Reported source ↗
Colt DCS and RMZ say Mumbai 3 will use 100 percent renewable energy. No supplier or PPA is named.
Water and cooling
CoolingHybrid air and liquid cooling Reported source ↗
Air cooling combined with direct liquid-to-chip cooling; closed-loop system with near-zero wastewater from cooling

Sources

  1. Colt acquires land in Navi Mumbai for 100MW data center (DCD, 2024-07-18)
  2. Colt signs $1.7bn joint venture in India with RMZ (DCD, 2024-11-19)
  3. Data Center Holdings India LLP: Rating assigned (ICRA, 2026-03-09)
  4. Colt DCS and RMZ start work on third facility at Mumbai campus, India (DCD, 2026-10-15)
  5. Colt DCS and RMZ Start Work on 64MW AI Data Centre in Mumbai (Data Centre Magazine, 2026-10-15)
  6. Colt DCS and RMZ Begin Construction of 64MW AI-Ready Data Centre in Navi Mumbai (Digital Terminal, 2026-10-16)
  7. RMZ Digital Infrastructure Partners (RMZ)
  8. Colt DCS, RMZ start 64MW Mumbai data centre construction after signing hyperscale client (CRN Asia, 2026-10-15)
  9. Colt DCS and RMZ commence construction on third Mumbai data center (W.Media, 2026-10-16)
  10. Minutes of 12th Consent Appraisal Committee Meeting of 2025-2026 (Maharashtra Pollution Control Board, 2025-12-01)
  11. Data Centre Holdings, India (Turner & Townsend)
  12. Half Yearly Compliance Report 2025 (Acknowledgement) (RMZ / MoEFCC, 2025-07-26)