Directory › China › Horinger and Hohhot › Kuaishou Horinger Computing Centre (快手和林格尔新区算力项目)

Kuaishou Horinger Computing Centre (快手和林格尔新区算力项目) data center

Horinger New Area, Hohhot, Inner Mongolia, China · Horinger and Hohhot market · location approximate to district level

Also listed as 快手和林格尔.

Kuaishou Horinger Computing Centre (快手和林格尔新区算力项目) is a data center project in Horinger New Area, Hohhot, China, operated by Kuaishou. It has been announced and has not yet reached the land or permitting stage. The operator has not published a capacity figure, and ArusGrid does not estimate one.

Latest change on record: entered the record as announced on 12 August 2026. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Announced
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Kuaishou
Hyperscaler self-build
AI workloads
Likely
Evidence grade
Sourced
Will it get built?Open question2 of 7 gates passed
○ Land secured○ Power arranged○ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Land secured.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Horinger and Hohhot holds 10 active projects with 298 MW of planned IT load between them, and Kuaishou Horinger Computing Centre (快手和林格尔新区算力项目) has no published figure so it sits outside that ranking. Of those, 3 are operational, 1 is operational and expanding, 1 is under construction, 2 are at the land and permitting stage and 3 are announced only. No third party publishes a colocation vacancy rate for Horinger and Hohhot, and ArusGrid does not estimate one.

Kuaishou has 2 others in China tracked by ArusGrid, including Kuaishou Intelligent Cloud Ulanqab Data Center and Kuaishou Xinghe Data Center, Ulanqab. It sits on the Kuaishou Horinger campus. The named user of the compute is Kuaishou (confirmed).

The stage was recorded as announced only on 12 August 2026. The money on record is CN¥10bn as of August 2026, the announced investment.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 2 public sources for this project, the latest dated 12 October 2026, and last checked the record on 19 October 2026.

How well evidenced is it

One or two hard signals sit behind the announcement. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesNo
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

A computing centre for Kuaishou's own use in a cluster that is mostly intelligent computing.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Stage history

2026-08-12Announced · cnfin.com

Who is behind it

OperatorKuaishou · Hyperscaler self-build

Who uses the compute

Own use · hyperscalerKuaishou · confirmed

as of 2026-08-12

Xinhua Finance says Kuaishou's computing project of over 10 billion yuan has landed in the Horinger New Area.

Source · 为何全球算力看中国 中国绿算看内蒙古 (Xinhua Finance (新华财经), 2026-08-12)

Money at this site

Announced investment, 2026-08CN¥10bn

Colocation price per kW of IT load per month

An own-use build. No colocation price applies.

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-10-19

  1. 为何全球算力看中国 中国绿算看内蒙古 (Xinhua Finance (新华财经), 2026-08-12)
  2. 世界算力竞逐,内蒙古何以崛起? (新华每日电讯, 2026-10-12)

More in Horinger and Hohhot

Also run by Kuaishou

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.