Also listed as 中金数据和林格尔 and CICC Horinger.
CICC Data Horinger Zero-Carbon Computing Base (中金数据和林格尔零碳算力基地项目) is a data center project in Horinger New Area, Hohhot, China, operated by Shengshu Technology (Hohhot) Co. (盛数科技(呼和浩特)有限公司), CICC Data project. It is at the land and permitting stage. The operator has not published an IT load figure. It is planned for 81,730 racks. ArusGrid does not convert racks into MW.
Latest change on record: entered the record as land and permitting on 19 August 2026. Record last checked against its sources on 19 October 2026.
Next gate to watch: Land secured.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
Horinger and Hohhot holds 10 active projects with 298 MW of planned IT load between them, and CICC Data Horinger Zero-Carbon Computing Base (中金数据和林格尔零碳算力基地项目) has no published figure so it sits outside that ranking. Of those, 3 are operational, 1 is operational and expanding, 1 is under construction, 2 are at the land and permitting stage and 3 are announced only. No third party publishes a colocation vacancy rate for Horinger and Hohhot, and ArusGrid does not estimate one.
CICC Data has 1 other in China tracked by ArusGrid, including CICC Data Ulanqab Low-Carbon Computing Base. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.
The stage was recorded as at the land and permitting stage on 19 August 2026. The money on record is CN¥4.96bn as of August 2026, the announced investment.
The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 2 public sources for this project, the latest dated 25 August 2026, and last checked the record on 19 October 2026.
One or two hard signals sit behind the announcement. The rules are fixed and published on the Methodology page.
No public signal either way.
A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.
Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.
No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.