NetEase Gui'an Data Center (网易贵安数据中心)

Gui'an New Area, Guizhou, China · Gui'an market · location approximate to district level

Also listed as 网易贵安 and NetEase Guian.

NetEase Gui'an Data Center (网易贵安数据中心) is a data center project in Gui'an New Area, China, operated by Guizhou NetEase Shuwang Technology (贵州网易数网科技有限公司). It is operational. The operator has not published an IT load figure. It is planned for 10,000 racks. ArusGrid does not convert racks into MW.

Latest change on record: moved to operational on 31 December 2023. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Guizhou NetEase Shuwang Technology (贵州网易数网科技有限公司)
Hyperscaler self-build
AI workloads
No signal either way
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Gui'an holds 12 active projects with 90 MW of planned IT load between them, and NetEase Gui'an Data Center (网易贵安数据中心) has no published figure so it sits outside that ranking. Of those, 5 are operational, 4 are operational and expanding and 3 are under construction. No third party publishes a colocation vacancy rate for Gui'an, and ArusGrid does not estimate one.

It is the only NetEase project ArusGrid tracks. The named user of the compute is NetEase (confirmed).

The dated record runs from under construction on 1 February 2023 to operational on 31 December 2023.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 3 public sources for this project, the latest dated 26 August 2026, and last checked the record on 19 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusNo signal either way

Sources describe it as NetEase's core business and warm-data platform. No AI or GPU deployment is stated.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Stage history

2023-02-01Under construction · sohu.com
2023-12-31Operational · rb.gywb.cn

Who is behind it

OperatorGuizhou NetEase Shuwang Technology (贵州网易数网科技有限公司) · Hyperscaler self-build

Who uses the compute

Own useNetEase · confirmed

Facility · as of 2024-08-28

Guiyang Daily says the centre began trial operation at end-2023 and already carries NetEase Mail and Youdao Dictionary live services.

Source · 裂变式突破 跨越式发展——贵安新区全力打造具有国际竞争力的智算基地 (贵阳日报, 2024-08-28)

Colocation price per kW of IT load per month

An own-use build. No colocation price applies.

Project team
Main contractor中建四局一公司 (China Construction Fourth Engineering Division, First Company) · Mar 2023 Reported source ↗
Construction of the 55,000 sqm campus with two halls, a generator building and an office
Land
Site109 mu · Jun 2023 Reported source ↗
109 mu site with about 55,000 sqm of floor area: two machine-room buildings, a diesel generator building and an office building.

Sources checked 2026-10-19

  1. 裂变式突破 跨越式发展——贵安新区全力打造具有国际竞争力的智算基地 (贵阳日报, 2024-08-28)
  2. 10000机架 网易贵安数据中心项目主体结构封顶 (IDC圈 (via Sohu), 2023-06-21)
  3. 算力向西 活力奔涌——贵州加快建设面向全国的算力保障基地 (贵州日报 via 中国日报网, 2026-08-26)

More in Gui'an

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.