ArusGridProject
Directory › China › Gui'an › Midea Gui'an Cloud Data Center (美的贵安云数据中心)

Midea Gui'an Cloud Data Center (美的贵安云数据中心)

Gui'an New Area, Guizhou, China · Gui'an market · location approximate to district level

Also listed as 美的贵安 and Midea Gui'an.

Midea Gui'an Cloud Data Center (美的贵安云数据中心) is a data center project in Gui'an New Area, China, operated by Midea Group (美的集团). It is operational. The operator has not published an IT load figure. It is planned for 10,000 racks. ArusGrid does not convert racks into MW.

Latest change on record: moved to operational on 26 August 2026. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Midea Group (美的集团)
Local developer
AI workloads
Likely
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Gui'an holds 12 active projects with 90 MW of planned IT load between them, and Midea Gui'an Cloud Data Center (美的贵安云数据中心) has no published figure so it sits outside that ranking. Of those, 5 are operational, 4 are operational and expanding and 3 are under construction. No third party publishes a colocation vacancy rate for Gui'an, and ArusGrid does not estimate one.

It is the only Midea Group project ArusGrid tracks. The named user of the compute is Midea Group (confirmed).

The dated record runs from under construction on 6 January 2023 to operational on 26 August 2026. Cooling uses hybrid air and liquid cooling, with a design PUE of 1.2.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 5 public sources for this project, the latest dated 26 August 2026, and last checked the record on 19 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Science and Technology Daily (2026-08-26) says more than 13,000 AI agents run on it every day.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Stage history

2023-01-06Under construction · gzstv.com
2026-08-26Operational · stdaily.com

Who is behind it

OperatorMidea Group (美的集团) · Local developer

Who uses the compute

Own use · enterpriseMidea Group · confirmed

as of 2024-09-09

Midea's own cloud project: a data centre, a cloud platform and a software R&D centre.

Source · 入局数据中心建设运维,美的楼宇科技扩大ToB版图 | 科技前线 (钛媒体, 2024-09-09)

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Project team
Mechanical and electrical works美的楼宇科技 (Midea Building Technologies), with 美控智慧建筑 for power · Sep 2024 · completed Reported source ↗
Integrated HVAC, elevators and power systems for Building A. Power covers integrated power cabinets, transformers, UPS and lithium batteries with installation and maintenance.
Water and cooling
CoolingHybrid air and liquid cooling · design PUE 1.2 Reported source ↗
Building A uses direct air AHU free cooling with chilled water top-up. The plant has two 800RT variable speed centrifugal chillers and one 800RT magnetic bearing chiller. The article says PUE reached as low as 1.17 and Midea commits to below 1.2 for five years.
WaterMidea Building Technologies Confirmed source ↗
CoolingHybrid air and liquid cooling · design PUE 1.2 Confirmed source ↗
Building B uses 350kW evaporative AHUs with water coil free cooling and compressor top-up. Cold plate liquid cooling with CDUs supports racks up to 54kW. 36 of 1,626 racks are liquid cooled.

Sources checked 2026-10-19

  1. 入局数据中心建设运维,美的楼宇科技扩大ToB版图 | 科技前线 (钛媒体, 2024-09-09)
  2. 算力向西,贵州炼成中国算力高地 (科技日报, 2026-08-26)
  3. Gui’an Midea Cloud (Midea Building Technologies)
  4. 影响力 | 贵安美的云数据中心开园 (贵州广播电视台, 2024-03-21)
  5. 贵安美的云一期B栋数据中心主体结构封顶 (人民网贵州频道, 2025-12-19)

More in Gui'an

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.