Also listed as 亚马逊云计算中卫合作项目(西云数据), NWCD and AWS Ningxia.
AWS China (Ningxia) Region data centres, Zhongwei is a data center project in Zhongwei, China, operated by Ningxia Western Cloud Data Technology (NWCD, 宁夏西云数据). It is operational. The operator has not published an IT load figure. It is planned for 10,800 racks, with 4,200 in service. ArusGrid does not convert racks into MW.
Latest change on record: moved to operational on 17 March 2026. Record last checked against its sources on 19 October 2026.
This project is built or running, so every gate counts as passed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
Zhongwei holds 18 active projects with 3,558 MW of planned IT load between them, and AWS China (Ningxia) Region data centres, Zhongwei has no published figure so it sits outside that ranking. Of those, 5 are operational, 5 are operational and expanding, 3 are under construction, 3 are at the land and permitting stage and 2 are announced only. No third party publishes a colocation vacancy rate for Zhongwei, and ArusGrid does not estimate one.
Amazon has 2 projects elsewhere in the dataset tracked by ArusGrid, including AWS Airoli and AWS Powai. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.
The dated record runs from operational on 14 December 2017 to operational on 17 March 2026. The money on record is US$2.5bn as of September 2023, the announced investment.
The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 5 public sources for this project, the latest dated 17 March 2026, and last checked the record on 19 October 2026.
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
No public signal either way.
A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.
Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source
Built for Ningxia Western Cloud Data Technology (NWCD, 宁夏西云数据)'s own use. No customer workload has been tied to this building on the public record.
The figure covers the whole campus.
An own-use build. No colocation price applies.
All projects in Zhongwei · All projects in China · All Amazon projects · All projects operational · Full directory