ArusGridProject
Directory › China › Zhongwei › Baidu Zhongwei AI Computing Centre

Baidu Zhongwei AI Computing Centre data center

Zhongwei, Ningxia, China · Zhongwei market · location approximate to city level

Also listed as 百度智算中心(中卫).

Baidu Zhongwei AI Computing Centre is a data center project in Zhongwei, China, operated by Baidu (百度). It is operational. The operator has not published a capacity figure, and ArusGrid does not estimate one.

Latest change on record: entered the record as operational on 17 September 2025. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Baidu (百度)
Hyperscaler self-build
AI workloads
Confirmed
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Zhongwei holds 18 active projects with 3,558 MW of planned IT load between them, and Baidu Zhongwei AI Computing Centre has no published figure so it sits outside that ranking. Of those, 5 are operational, 5 are operational and expanding, 3 are under construction, 3 are at the land and permitting stage and 2 are announced only. No third party publishes a colocation vacancy rate for Zhongwei, and ArusGrid does not estimate one.

It is the only Baidu project ArusGrid tracks. The named user of the compute is Baidu (reported, unconfirmed).

The stage was recorded as operational on 17 September 2025.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 3 public sources for this project, the latest dated 31 August 2026, and last checked the record on 19 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

Described as an AI computing centre (智算中心) with about 11,000 PFLOPS of compute (潮新闻, Aug 2026).

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Stage history

2025-09-17Operational · nx.people.com.cn

Who is behind it

OperatorBaidu (百度) · Hyperscaler self-build

Who uses the compute

Own use · hyperscalerBaidu · reported, unconfirmed

Colocation price per kW of IT load per month

An own-use build. No colocation price applies.

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-10-19

  1. 中卫市刷新数据中心集群建设进度条 (人民网宁夏频道, 2025-09-17)
  2. 潮声丨算力产业“下沉”,五线小城站上AI风口 (潮新闻 via 腾讯新闻, 2026-08-31)
  3. 中卫数据中心集群建设成效显著 (中卫市人民政府, 2026-02-04)

More in Zhongwei

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.