SDAIA Salboukh data centre is a data center project in Salboukh, Saudi Arabia, operated by SDAIA (Saudi Data and AI Authority). It is at the land and permitting stage. It is planned for 20 MW of IT load.
Latest change on record: entered the record as land and permitting on 8 July 2025.
Next gate to watch: Land secured.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Saudi Arabia approves, powers and taxes data centers is on Data center rules in Saudi Arabia.
Construction or financing is evidenced, or several independent signals agree. On record: named funder, disclosed client (confirmed), dated source in the last 24 months. Criteria.
No public signal either way.
Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria.
Case-by-case authorisation only · Case-by-case authorisation only (2025-11-19) source
All projects in Riyadh · All projects in Saudi Arabia · All SDAIA projects · All projects at the land and permitting stage · Data center rules in Saudi Arabia · Full directory
Project team on other projects: AlBawani