Riyadh, Saudi Arabia · Riyadh market · location approximate to city level
Humain Riyadh campus is a data center project in Riyadh, Saudi Arabia, operated by Humain. It is under construction. It is planned for 100 MW of IT load.
Latest change on record: entered the record as under construction on 26 August 2025.
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed✓ Construction started
Next gate to watch: Tenant or own use.
Your call. Will it be built?
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
Construction or financing is evidenced, or several independent signals agree. On record: named funder, dated, sized phase, three or more sources, dated source in the last 24 months. Criteria.
AI workloads
StatusLikely
Purpose-built by a state AI company, with an Nvidia partnership covering GB300 accelerators. Stated AI purpose.
Access to AI chips
GradeGovernment-confirmed
A dated US government document names this project's operator, its parent, or a named funder as authorised to receive advanced computing items. Criteria.
Humain · Commerce Department authorisation of 2025-11-19 for up to 35,000 Nvidia GB300 accelerators, case by case, subject to security and reporting conditions with ongoing BIS monitoring. (2025-11-20) source
Case-by-case authorisation only · Case-by-case authorisation only (2025-11-19) source
Phases
Initial capacity · Under construction100 MW, target Q2 2026