DAMAC Digital RUH-1 (Riyadh Industrial City 2) is a data center project in Riyadh, Saudi Arabia, operated by DAMAC Digital (EDGNEX). It is operational. It is planned for 20 MW of IT load.
Latest change on record: moved to operational on 4 June 2026.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Saudi Arabia approves, powers and taxes data centers is on Data center rules in Saudi Arabia.
Running capacity. The site is operational or expanding. On record: named funder, three or more sources, dated source in the last 24 months. Criteria.
The operator markets AI-optimised infrastructure at company level but discloses no tenant, workload or cooling specification for this site.
Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria.
Case-by-case authorisation only · Case-by-case authorisation only (2025-11-19) source
Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.