How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusConfirmed
Nvidia GB200 NVL72 deployed, liquid-cooled (Oct 2025)
Phases
JDC1 (colo, Sea anchor) · Operational48 MW, target 2024
JDC2 (Nvidia GB200 AI DC, YTL AI Cloud) · Operational20 MW, target 2025
JDC3 (2nd AI DC) · Under constructionSize not published
JDC6 (built-to-suit MNC) · Operational40 MW, target 2025
Who is behind it
OperatorYTL Power (YTL Data Center Holdings) · Colocation
Funder, EquityYTL Power International
Client, confirmedSea Ltd
Money at this site
Announced investment, 2022-08RM15bn (about US$3.3bn)
The figure covers the whole campus.
Platform deals that include it
YTL-Nvidia AI infrastructure deal
Platform capital, 2023-12US$2.2bn
Platform capital spans several sites. It is never added to this project's own figure.
Land
Land sellerBoustead Plantations · 664 ha · RM428.8m (≈US$97m) · Sep 2021 Confirmed source ↗ Five parcels, buyer SIPP Power (70% YTL Power)
Power supply
Grid supplyNational grid (TNB) · 600 MW · Nov 2025 Reported source ↗ 500MW solar plant planned on site · 600MW from national grid as backup to solar · Applies to the whole campus.
Own generationSIPP Power (YTL Power) and TNB · 215 MW · Jun 2026 Reported source ↗ Co-located solar, about 215MW by end-2026 and 600MW long term · Applies to the whole campus.
Water and cooling
CoolingDirect liquid cooling Reported source ↗ Liquid-cooled Nvidia GB200 NVL72 systems (facility-stated)