Bridge Data Centres MY07

Ulu Tiram, Johor, Malaysia · Johor market · location approximate to district level

Bridge Data Centres MY07 is a data center project in Ulu Tiram, Malaysia, operated by Bridge Data Centres (Chindata/Bain). It is under construction. It is planned for 200 MW of IT load.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
200 MW
Running now
Not disclosed
Operator
Bridge Data Centres (Chindata/Bain)
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Builder appointed.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. On record: named funder, disclosed client (reported), three or more sources, dated source in the last 24 months. Criteria.

AI workloads

StatusLikely

ByteDance reported; 400MW grid ESA

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria.

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Who is behind it

OperatorBridge Data Centres (Chindata/Bain) · Colocation
Funder, EquityBain Capital
Funder, DebtBank syndicate ($2.8B loan, APAC portfolio)

Who uses the compute

Tenant · hyperscalerByteDance · reported, unconfirmed

Money at this site

ArusGrid estimate, building costabout US$1.9bn to US$2.9bn

No figure has been announced. This range is 200 MW of planned IT load times a published benchmark of US$11.37 per watt for Malaysia, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Platform deals that include it

ByteDance Malaysia cumulative commitment
Country programme, 2026-01
US$6.6bn

Platform capital spans several sites. It is never added to this project's own figure.

Power supply
Grid supplyTenaga Nasional Berhad (TNB) · 400 MW · Nov 2024 Reported source ↗
MY07 ESA, Ulu Tiram; via TNB Green Lane Pathway
Renewable power dealTNB Renewables Sdn Bhd · Nov 2024 Reported source ↗
CRESS Bilateral Energy Supply Contract Head of Terms; MW not stated · Heads of terms only, not a final BESC
Green tariffTenaga Nasional Berhad (TNB Renewables Sdn Bhd for green supply) · 400 MW · Jan 2025 Reported source ↗
Bilateral Energy Supply Contract heads of terms under the Corporate Renewable Energy Supply Scheme (CRESS), first partner under the framework. · MY07 Electricity Supply Agreement for the Ulu Tiram site.
Water and cooling
WaterRecycled wastewater · Johor Special Water / IWK (treated effluent from JB-Pelangi STP), BDC-operated Ulu Tiram water reclamation plant · 5 MLD Reported source ↗
MBR + RO plant producing since 2025-06-09; 4 MLD at start (w.media), 5 MLD now, expansion to 20 MLD planned; RO by Suntar International
WaterRecycled wastewater · Johor Special Water (treated effluent from IWK plants) Confirmed source ↗
The Johor Menteri Besar said Bridge Data Centres' site in the Ulu Tiram Industrial Area began producing reclaimed water on 9 June 2025. This is earlier than the Q4 2025 full operation date in the held August 2025 release.
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedTenaga Nasional Berhad (TNB) · Grid supply · Mar 2024 source ↗
This project is one of 2 that fit. The other is Bridge Data Centres MY06.
UnconfirmedParagon Globe Bhd subsidiary (not named) · Piling and earthworks · RM45.16m · Sep 2026 source ↗
This project is one of 3 that fit. The others are EdgeConneX Johor, STACK JHB01.

Sources

  1. mingtiandi.com
  2. datacenterdynamics.com
  3. bridgedatacentres.com
  4. Bridge Data Centres, TNB sign MY07 400MW deal and green energy partnership, boosting Malaysia as a digital hub (Digital News Asia, 2024-12-04)
  5. Johor First State To Adopt Tier 4 Data Centre Technology - Onn Hafiz (Bernama, 2025-08-11)