How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsNo
AI workloads
StatusConfirmed
next-gen hyperscale AI design per operator
Phases
Bldg 1 of 5 (40MW each) · Under construction40 MW, target 2026
Who is behind it
OperatorEmpyrion Digital · Colocation
Funder, EquitySeaTown Holdings (Temasek unit)
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Power supply
Grid supplyTenaga Nasional Berhad (TNB) · 145 MW · Dec 2025 Confirmed source ↗ Long-term green PPAs mentioned, no counterparty · Initial 145MW allocation, energisation from Sep 2026 · Applies to the whole campus.
Water and cooling
CoolingHybrid air and liquid cooling · design PUE <1.3 (liquid) / <1.4 (air) Reported source ↗ Liquid and air-cooled halls; PUE target <1.3 liquid, <1.4 air
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedWest River Bhd · Grid and substation works · RM22.56m (≈US$5m) · Aug 2026 source ↗ This project is one of 3 that fit. The others are STACK JHB01, Digital Hyperspace Johor.