How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsNo
AI workloads
StatusConfirmed
AI-ready hyperscale design per operator
Phases
JHB01A · Under construction120 MW, target 2026
JHB01B · Announced100 MW
Who is behind it
OperatorSTACK Infrastructure (APAC) · Colocation
Funder, EquityIPI Partners / Blue Owl
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Money at this site
Approved by a government investment agency, 2025-01RM7bn (about US$1.7bn)
An approval figure is an incentive ceiling. It often covers a first phase and can exclude land or IT equipment.
The figure covers the whole campus.
Power supply
Dedicated substationTenaga Nasional Berhad (TNB) · 275kV · Jan 2025 Confirmed source ↗ 275kV infrastructure with on-site substation · Applies to the whole campus.
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedJati Tinggi Holding Sdn Bhd · Grid and substation works · RM10.56m (≈US$2m) · Jul 2026 source ↗ This project is one of 3 that fit. The others are Microsoft Nusa Cemerlang (Mukim Pulai), EdgeConneX Johor.
UnconfirmedWest River Bhd · Grid and substation works · RM22.56m (≈US$5m) · Aug 2026 source ↗ This project is one of 3 that fit. The others are Digital Hyperspace Johor, Empyrion Digital MY1.