How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesNo
Dated source in the last 24 monthsNo
AI workloads
StatusLikely
ByteDance confirmed anchor tenant
Phases
Phase 1 (Bldg 1 of 3) · OperationalSize not published, target 2022
Who is behind it
OperatorBridge Data Centres (Chindata/Bain) · Colocation
Funder, EquityBain Capital
Client, confirmedByteDance
Money at this site
Announced investment, 2021-12RM2.5bn (about US$595m)
The figure covers the whole campus.
Platform deals that include it
ByteDance Malaysia cumulative commitment
Country programme, 2026-01US$6.6bn
Platform capital spans several sites. It is never added to this project's own figure.
Power supply
Dedicated substationTenaga Nasional Berhad (TNB) · 275kV · Oct 2022 Confirmed source ↗ PMU Sedenak 275/132kV (RM68m, done Aug 2019; RM1.2m upgrade Sep 2022); names Bridge Data Center as customer; shared area substation · Applies to the whole campus.
Water and cooling
WaterRainwater harvesting Confirmed source ↗ Rainwater harvesting saves ~1,340 m3/yr; main supply not stated (The Star 2026-07-23 says Sedenak site uses freshwater)
CoolingEvaporative cooling Confirmed source ↗ Campus uses cooling towers; drainage optimisation cut cooling tower water use ~16,000 m3 in 2025 (facility-stated)
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedTenaga Nasional Berhad (TNB) · Grid supply · Mar 2024 source ↗ This project is one of 2 that fit. The other is Bridge Data Centres MY07.