K2 JHR1 Campus
Sedenak (Kulai), Johor, Malaysia · Johor market · location approximate to district level
K2 JHR1 Campus is a data center project in Sedenak (Kulai), Malaysia, operated by K2 Strategic (Kuok Group). It is operational and expanding. The published capacity figure is 84 MW, and its basis is not stated as IT load. The operator reports 40 MW running.
Planned IT load
84 MW
unstated
Operator
K2 Strategic (Kuok Group)
Colocation
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.
How well evidenced is it
Running capacity. The site is operational or expanding. On record: named funder, dated, sized phase, three or more sources, dated source in the last 24 months. Criteria.
AI workloads
StatusLikely
234MW modern greenfield (2023+)
Access to AI chips
GradeNo US licence required
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.
Phases
Phase 1 (opened Oct 2024) · Operational40 MW, target 2024
JHR01-03 balance · Announced20 MW
JHR04 (Phase 4) · Under construction24 MW, target 2026
Who is behind it
OperatorK2 Strategic (Kuok Group) · Colocation
Funder, EquityKuok Group
Who uses the compute
Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.
Project team
Core and shell builderSunway Construction · RM192.88m (≈US$43m) · Oct 2023 Confirmed source ↗ Build contract, letter of initial appointment
Core and shell builderSunway Construction · RM132.7m (≈US$30m) · Feb 2025 Confirmed source ↗ Stages 1 and 2
Core and shell builderSunway Construction · RM260m (≈US$59m) · May 2025 Confirmed source ↗ Stage 3, final phase
Land
Industrial estateSedenak Tech Park (JCorp / TPM Technopark) · 60 acres Reported source ↗ K2 building on a 60-acre parcel in Sedenak Tech Park; seller/terms not stated
Power supply
Grid supplyTNB · 300 MW · 275kV · Apr 2024 Confirmed source ↗ Electricity Supply Agreement; 300MW is gross grid capacity; 275kV interim supply · Applies to the whole campus.
Water and cooling
CoolingHybrid air and liquid cooling · design PUE <1.38x Confirmed source ↗ JHR04 building: air and liquid hybrid cooling (JHR01-03 are direct air)
CoolingAir cooled · design PUE 1.4 Confirmed source ↗ Direct air cooled
Sources
- k2strategic.co
- w.media
- dcbyte.com
- JHR01-03 Kulai, Johor (K2 Strategic)
- JHR04 Kulai, Johor (K2 Strategic)
- K2 STRATEGIC INFRASTRUCTURE MALAYSIA SDN BHD @ SEDENAK - K2 DATA CENTRE (PHASE 4) (myBina (BCI), 2026-03-30)
- Loan facility and revolving credit facility of up to an aggregate amount of US$140 million granted by group of onshore and offshore lenders to K2 Strategic Infrastructure Malaysia Sdn. Bhd. (Rahmat Lim & Partners, 2026-07-24)
- IJM said to have bagged K2 data centre construction job (The Edge Malaysia, 2026-10-26)
- Billionaire Robert Kuok's grandson drives $10 billion bet on AI data centres (Forbes Australia (Forbes Asia), 2025-04-27)