Bitdeer AI Johor campus (A201, A202) is a data center project in Johor Bahru, Malaysia. It has been announced and has not yet reached the land or permitting stage. It is planned for 87 MW of IT load.
Latest change on record: entered the record as announced on 14 September 2026.
Next gate to watch: Land secured.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.
Construction or financing is evidenced, or several independent signals agree. On record: disclosed client (confirmed), dated, sized phase, three or more sources, dated source in the last 24 months. Criteria.
Leased by Bitdeer AI, a GPU cloud operator, for its AI cloud under a 10-year data centre services agreement. No site-level cooling or rack disclosure.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.
87 MW · A201 21.7MW (live) plus A202 65.1MW under a ten-year data centre services agreement, energisation Q3 2027; A201 over 70% off-take committed to unnamed customers · as of 2026-09-30
Bitdeer's own release of 2026-09-14 announces the ten-year agreement for the 65.1MW A202 facility at its existing Johor Bahru campus, taking the campus to 86.8MW; 2026-09-30 announces off-take commitments of more than 70% of A201's 21.7MW with over US$1.7bn expected revenue over five years. Landlord and off-takers are not named in either release.
Source · Bitdeer AI Secures 65.1MW A202 Facility at Its Existing Johor, Malaysia Campus; Estimated Active AI Cloud Pipeline Surpasses $7 Billion (Bitdeer Technologies Group, 2026-09-14)
Source · Bitdeer AI Further Expands AI Cloud Services with Off-take Commitments of more than 70% of Its 21.7MW A201 Malaysia Data Center (GlobeNewswire via Manila Times, 2026-09-30)
No figure has been announced. This range is 87 MW of planned IT load times a published benchmark of US$11.37 per watt for Malaysia, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.
Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.
Platform capital spans several sites. It is never added to this project's own figure.
All projects in Johor · All projects in Malaysia · All projects announced only · Data center rules in Malaysia · Full directory