How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusConfirmed
liquid cooling for AI densities (operator)
Phases
Phase 1 (64MW, first 20MW RFS Sep 2026) · Under construction64 MW, target 2026
Phase 2 (136MW, acceleration under discussion) · Announced136 MW
Who is behind it
OperatorTM Nxera (Telekom Malaysia + Singtel Nxera JV) · Joint venture
Funder, Joint venture partnerTelekom Malaysia
Funder, Joint venture partnerSingtel (Nxera)
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Who builds it
Design and build contractorIJM Construction Sdn Bhd · RM331.7m (≈US$75m) · Jun 2024 · completed Confirmed source ↗ Iskandar Puteri DC Block 2 design and construct incl. M&E and fit-out, Tier III; Jul 2024 to 3Q2025
Power supply
Grid supplyTenaga Nasional Berhad (TNB) · 280 MW · Jan 2026 Reported source ↗ ESA for ~200MW IT campus, Iskandar Puteri · Applies to the whole campus.
Water and cooling
CoolingDirect liquid cooling Reported source ↗ Liquid cooling (facility-stated, type not detailed)