ArusGridCity
Directory › Malaysia › Johor › Johor Bahru

Data centers in Johor Bahru

Malaysia · dataset updated 2026-10-02

ArusGrid tracks 6 active data center projects in Johor Bahru, Malaysia, with 607 MW of planned IT load. Of these, 1 is operational, 1 is operational and expanding and 4 are announced only.

Johor Bahru sits in the Johor market, which is the level at which brokers publish vacancy and ArusGrid compares supply. The largest project is CURRENC AI Data Center at 500 MW, announced only. The operators with the most planned capacity here are CURRENC Group (Nasdaq fintech) (500 MW across 1 project), Open DC (20 MW across 1 project) and DayOne (1 project).

Open the mapPipeline view

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
CURRENC AI Data CenterJohor BahruAnnounced500undisclosedCURRENC Group (Nasdaq fintech)Likely
Bitdeer AI Johor campus (A201, A202)Johor BahruAnnounced87undisclosedUndisclosed landlordLikely
Open DC JB1Johor BahruOperational20undisclosedOpen DC Sdn BhdUnlikely
DayOne Kempas Tech Park CampusJohor Bahru (Kempas)Expandingnone publishedundisclosedDayOne (ex-GDS International)Confirmed
EdgeConneX JohorJohor BahruAnnouncednone publishedundisclosedEdgeConneXNo signal either way
Microsoft Eco Business Park IJohor Bahru (Eco Business Park I)Announcednone publishedundisclosedMicrosoftLikely

Market pages

Other cities in Malaysia

Operators here with their own page

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.