How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusConfirmed
Hosts Lintasarta's GPU Merdeka sovereign AI cloud running Nvidia H100 SXM GPU servers (live 2024); BDx says CGK4 is Indonesia's first Nvidia DGX-Ready-certified campus and supports up to 120kW/rack.
Phases
Phase 1 · OperationalSize not published, target 2024
AI Campus 2 Building 1 of 6 · Under construction120 MW, target 2027
Who is behind it
OperatorBDx Indonesia · Joint venture
Funder, EquityI Squared Capital
Funder, Joint venture partnerIndosat Ooredoo Hutchison
Funder, Joint venture partnerLintasarta
Client, confirmedLintasarta (GPU Merdeka sovereign AI cloud)
Platform deals that include it
BDx and PLN 1.2 GW national power commitment
Power deal, 2026-06Not disclosed
BDx Indonesia US$320m loan (Permata, BCA, KB Bank)
Debt, 2026-04-01US$320m
Platform capital spans several sites. It is never added to this project's own figure.
Power supply
Grid supplyPLN · 788 MVA · Jun 2026 Reported source ↗ Bisnis: designed in line with renewable sources, unquantified · Part of BDx 1.2 GW PLN commitment; 788 MVA initial, max 2 x 380 MVA per ANTARA; Selular (2026-09-22) cites 845 MVA
Dedicated substationPLN · 150kV · Jun 2026 Reported source ↗ PLN building new 150 kV GI Jatiluhur with two dedicated line bays for the campus
Power allocation or planPerum Jasa Tirta (PJT) · Sep 2026 Reported source ↗ Hydroelectric scheme under study · Exploring hydro supply from Jatiluhur Dam (~5 km); not a signed deal
Water and cooling
CoolingDirect liquid cooling Reported source ↗ Liquid cooling technology (campus-stated, type not detailed)