How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsNo
AI workloads
StatusLikely
PDG describes JC3 as 'flexible design tailored to support both hyperscale and AI infrastructure deployments'; 120MW modern greenfield; May 2026 financing PR says the raise was 'on the back of customer success' implying anchor hyperscale pre-lease.
Phases
Phase 1 (Building 1) · Under constructionSize not published, target 2026
Building 2 · AnnouncedSize not published
Who is behind it
OperatorPrinceton Digital Group · Colocation
Funder, DebtDBS
Funder, DebtHSBC
Funder, DebtMaybank
Funder, DebtSMBC
Funder, DebtStandard Chartered
Client, reported, unconfirmedUndisclosed hyperscaler
Money at this site
Announced investment, 2025-01US$1bn
The figure covers the whole campus.
Platform deals that include it
PDG ~US$856M green financing for JC3
Debt, 2026-05US$856m
Platform capital spans several sites. It is never added to this project's own figure.
Land
Land sellerPT Puradelta Lestari Tbk (DMAS), GIIC Kota Deltamas · Rp171bn (≈US$11m) · 2024 Inferred by ArusGrid source ↗ Customer-level revenue from PDG in DMAS 2024 reporting
Why we think so. DMAS reported PT Princeton Digital Group as a 2024 land customer at Deltamas; PDG's only Deltamas site bought in 2024 is JC3 (JC4 land was bought in 2026).
Power supply
Dedicated substationPLN · 200 MVA · 150kV · Sep 2026 Reported source ↗ GI 150 kV Sukamahi energized, prepared to supply PDG JC3 up to 200 MVA