Data center projects on hold

Southeast Asia, the Gulf and India · dataset updated 2026-09-27

Projects on hold have been paused by the operator or the authorities, with a dated source for the pause.

ArusGrid records 3 projects on hold, with 29 MW of planned IT load, led by Indonesia (1 project, 24 MW), the Philippines (1 project, 5 MW) and Bahrain (1 project, 0 MW). The largest is SpaceDC JAK1 (ID01 campus), West Jakarta at 24 MW in Greater Jakarta. The operators with the most capacity at this stage are SpaceDC (24 MW), EdgeConneX (5 MW) and AWS.

Pipeline viewOpen the map

Indonesia 1 project · 24 MW

ProjectCityStagePlanned MWRunning MWOperatorAI
SpaceDC JAK1 (ID01 campus), West JakartaWest Jakarta (Kalideres)On hold24undisclosedSpaceDCUnlikely

Philippines 1 project · 5 MW

ProjectCityStagePlanned MWRunning MWOperatorAI
EdgeConneX / Aboitiz InfraCapital MNL01Metro Manila (site not disclosed)On hold5undisclosedEdgeConneX / Aboitiz InfraCapital JVNo signal either way

Bahrain 1 project · 0 MW

ProjectCityStagePlanned MWRunning MWOperatorAI
AWS Middle East (Bahrain) region, me-south-1ManamaOn holdnone publishedundisclosedAmazon Web ServicesNo signal either way

Other stages

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.