China Unicom Wujiang Computing Centre (中国联通吴江算力中心) data center

Suzhou, Jiangsu, China · Qingpu-Wujiang-Jiashan market · location approximate to district level

China Unicom Wujiang Computing Centre (中国联通吴江算力中心) is a data center project in Suzhou, China, operated by China Unicom Suzhou (中国联通苏州分公司). It is at the land and permitting stage. The operator has not published an IT load figure. It is planned for 10,000 racks. ArusGrid does not convert racks into MW.

Latest change on record: entered the record as land and permitting on 25 April 2025. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Land and permitting
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
China Unicom Suzhou (中国联通苏州分公司)
Telco
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Long shot1 of 7 gates passed
✓ Land secured○ Power arranged○ Approvals granted○ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Qingpu-Wujiang-Jiashan holds 6 active projects with 0 MW of planned IT load between them, and China Unicom Wujiang Computing Centre (中国联通吴江算力中心) has no published figure so it sits outside that ranking. Of those, 2 are operational, 3 are operational and expanding and 1 is at the land and permitting stage. No third party publishes a colocation vacancy rate for Qingpu-Wujiang-Jiashan, and ArusGrid does not estimate one.

China Unicom has 9 others in China tracked by ArusGrid, including China Unicom Zhongwei Cloud Data Center, China Unicom (Huailai) Big Data Innovation Industrial Park (中国联通(怀来)大数据创新产业园) and China Unicom Southwest Data Center (Chongqing Shuitu). It sits on the Wujiang Economic and Technological Development Zone, Yinjia Road and Guangming Road campus. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The stage was recorded as at the land and permitting stage on 25 April 2025. The money on record is CN¥2.9bn as of April 2025, the announced investment.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 3 public sources for this project, the latest dated 14 August 2026, and last checked the record on 19 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Filing describes 10,000 high-power compute racks.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Phases

Two computing buildings, one substation, one O&M building · Land and permittingSize not published

Stage history

2025-04-25Land and permitting · cww.net.cn

Who is behind it

OperatorChina Unicom Suzhou (中国联通苏州分公司) · Telco

Who uses the compute

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.

Money at this site

Announced investment, 2025-04CN¥2.9bn

The figure covers the whole campus.

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
Industrial estate吴江经济技术开发区 · 63 mu · Apr 2025 Confirmed source ↗
site at 尹家路与光明路交叉口东北角. Seller not named.

Sources checked 2026-10-19

  1. 总投资超29亿元!中国联通吴江算力中心项目通过备案 (通信世界网, 2025-04-25)
  2. 中国移动、中国联通三大算力项目获备案:总投资超141亿元 (C114通信网 (新浪科技转载), 2025-04-26)
  3. 企业深化产业布局 算力网有望拉动4万亿元投资 (新华网 (from 经济参考报), 2026-08-14)

More in Qingpu-Wujiang-Jiashan

Also run by China Unicom

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.