ArusGridProject
Directory › China › Zhangjiakou › China Ruifeng Xuanhua AI Computing Centre (瑞风新能源宣化智算中心)

China Ruifeng Xuanhua AI Computing Centre (瑞风新能源宣化智算中心) data center

Xuanhua District, Zhangjiakou, Hebei, China · Zhangjiakou market · location approximate to district level

Also listed as 瑞风新能源宣化 and Ruifeng Xuanhua.

China Ruifeng Xuanhua AI Computing Centre (瑞风新能源宣化智算中心) is a data center project in Xuanhua District, Zhangjiakou, China, operated by China Ruifeng Renewable Energy (中国瑞风新能源, HKEX 00527). It is at the land and permitting stage. The operator has not published an IT load figure. It is planned for 3,000 racks. ArusGrid does not convert racks into MW.

Latest change on record: entered the record as land and permitting on 25 May 2026. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Land and permitting
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
China Ruifeng Renewable Energy (中国瑞风新能源, HKEX 00527)
Local developer
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Long shot1 of 7 gates passed
✓ Land secured○ Power arranged○ Approvals granted○ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Zhangjiakou holds 8 active projects with 540 MW of planned IT load between them, and China Ruifeng Xuanhua AI Computing Centre (瑞风新能源宣化智算中心) has no published figure so it sits outside that ranking. Of those, 3 are operational, 2 are under construction, 2 are at the land and permitting stage and 1 is announced only. No third party publishes a colocation vacancy rate for Zhangjiakou, and ArusGrid does not estimate one.

It is the only China Ruifeng Renewable Energy project ArusGrid tracks. Named users of the compute are ByteDance, Alibaba Cloud and Tencent Cloud (reported, unconfirmed).

The stage was recorded as at the land and permitting stage on 25 May 2026. The money on record is CN¥24bn as of February 2026, the announced investment.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 6 public sources for this project, the latest dated 24 June 2026, and last checked the record on 19 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

The HKEX filing describes an AI computing centre and a planned North China inference cluster.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Phases

Phase 1 · Land and permittingSize not published, target 2028

Stage history

2026-05-25Land and permitting · news.qq.com

Who is behind it

OperatorChina Ruifeng Renewable Energy (中国瑞风新能源, HKEX 00527) · Local developer

Who uses the compute

Tenant · hyperscalerByteDance · rumoured

Letter of cooperation intent only · as of 2026-02-17

Article says the company holds intent letters from ByteDance, Alibaba Cloud and Tencent Cloud for this project

Source · 这家连亏11年、资不抵债的风电“仙股”,要投240亿建智算中心 (腾讯新闻, 2026-02-17)

Tenant · hyperscalerAlibaba Cloud · rumoured

Letter of cooperation intent only · as of 2026-02-17

Same intent letter list for this project

Source · 这家连亏11年、资不抵债的风电“仙股”,要投240亿建智算中心 (腾讯新闻, 2026-02-17)

Tenant · hyperscalerTencent Cloud · rumoured

Letter of cooperation intent only · as of 2026-02-17

Same intent letter list for this project

Source · 这家连亏11年、资不抵债的风电“仙股”,要投240亿建智算中心 (腾讯新闻, 2026-02-17)

Money at this site

Announced investment, 2026-02CN¥24bn

The figure covers the whole campus.

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
Allocated by张家口市宣化经济开发区管理委员会 · 900 mu · Feb 2026 Reported source ↗
Framework investment agreement; land not yet transferred
Land seller张家口市自然资源和规划局宣化分局 (Zhangjiakou Natural Resources and Planning Bureau, Xuanhua branch) · 144,800 sqm · CNY 84.94m · leasehold · May 2026 Confirmed source ↗
50-year industrial land use right won at public tender on 2026-05-25 by subsidiary 星途智算算力. Four adjoining plots north of Zhaochuan town, Xuanhua, about 14.48 hectares (about 217 mu). Earmarked for phase 1 of the Xuanhua AI computing centre. Part of the 900 mu park already held.
Power supply
Power allocation or planFeb 2026 Confirmed source ↗
The project plans 100% direct supply of green electricity from local wind and solar under a government plus enterprise plus grid model. · The 200MW figure is a grid-side independent LFP storage station of 200MW/800MWh on about 55 mu, not the grid supply. The same announcement also cites 400MW/1600MWh elsewhere. The agreement is a non-binding framework. · Applies to the whole campus.
Water and cooling
Coolingdesign PUE 1.2 Confirmed source ↗
Phase 1 servers will use water-saving or non-water-consuming cooling methods. Racks are at least 12kW, built to Class A standard.

Sources checked 2026-10-19

  1. 风电公司大手笔:拟斥资240亿元投建智算项目 (同花顺财经, 2026-02-10)
  2. 瑞风新能源耗资8494万元成功竞得并收购河北张家口宣化区土地使用权 (腾讯新闻, 2026-05-26)
  3. LATEST BUSINESS DEVELOPMENT — XUANHUA ARTIFICIAL INTELLIGENCE COMPUTING POWER CENTRE PROJECT (China Ruifeng Renewable Energy Holdings (HKEX 00527), 2026-02-09)
  4. 中国瑞风新能源 :通过一般授权配售新股募资约 1.9 亿港元 发展算力中心及补充运营资金 (Huasheng Tong (华盛通), 2026-06-24)
  5. 这家连亏11年、资不抵债的风电“仙股”,要投240亿建智算中心 (腾讯新闻, 2026-02-17)
  6. 瑞风新能源(00527.HK)耗资8494万元成功竞得并收购河北张家口宣化区土地使用权 (格隆汇, 2026-05-26)

More in Zhangjiakou

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.