ArusGrid tracks 12 active data center projects in Batam and Bintan, Indonesia, with 835 MW of planned IT load. Of these, 3 are operational and expanding, 4 are under construction, 2 are at the land and permitting stage and 3 are announced only. Projects under construction or commissioning account for 523 MW and operational sites for 217 MW of planned capacity. Operators have disclosed 63 MW actually running, a figure most of them do not publish.
The largest project is DayOne Kabil Industrial Tech Park (KITP) at 360 MW, under construction. The operators with the most planned capacity here are DayOne (432 MW across 2 projects), BW Digital (120 MW across 1 project) and Princeton Digital Group (96 MW across 1 project). No third party publishes a colocation vacancy rate for Batam and Bintan, and ArusGrid does not estimate one.
Grid power for a large industrial user in Indonesia costs about US$0.062 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Indonesia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”.
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| DayOne Kabil Industrial Tech Park (KITP) | Batam | Under construction | 360 | undisclosed | DayOne (PT Digitalland Service One) | Confirmed |
| BW Digital NDP1 | Batam | Expanding | 120 | 24 | BW Digital | Confirmed |
| Princeton Digital Group BT1 | Batam | Under construction | 96 | undisclosed | Princeton Digital Group | Likely |
| Racks Central Batam (RCBI) | Batam | Land and permitting | 95 | undisclosed | Racks Central | Likely |
| DayOne Nongsa Digital Park Campus (NDP1-3) | Batam | Expanding | 72 | 34 | DayOne (PT Digitalland Service One) | Likely |
| NeutraDC Nxera Batam BTM-1 | Batam | Under construction | 51 | undisclosed | NeutraDC Nxera Batam | Confirmed |
| Golden Digital Gateway (Nongsa One) | Batam | Expanding | 25 | 5.2 | Golden Digital Gateway (Data Center First) | No signal either way |
| AESLER-GREENIX Mark 1 | Batam | Under construction | 16 | undisclosed | PT Aesler Grup Internasional Tbk | No signal either way |
| Altiva Identity Datacenter Nongsa | Batam (Nongsa) | Announced | none published | undisclosed | PT Altiva Identity Datacenter | No signal either way |
| DCI Bintan Campus (Hyperscale 3 / H3) | Bintan | Land and permitting | none published | undisclosed | DCI Indonesia | Likely |
| Quantum AI Data Center (WorldVuer iByond) | Batam | Announced | none published | undisclosed | WorldVuer iByond | No signal either way |
| Range IDC / Equator Gate System Batam AI Data Center | Batam | Announced | none published | undisclosed | Equator Gate System Batam (EGSB) / Range Intelligent Computing | Likely |
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| Pusat Data Nasional 2 (National Data Center Batam) | Batam | Cancelled | none published | undisclosed | Kementerian Komunikasi dan Digital (Komdigi) | No signal either way |
DayOne · Princeton Digital Group · Racks Central · NeutraDC (Telkom) · DCI Indonesia
All projects in Indonesia · Full directory