How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusConfirmed
Gorilla Technology signed a US$2.5bn five-year GPUaaS compute contract (Jun 2026) to deploy Nvidia B300 GPU servers at this facility, phase 1 of 1,000 B300 servers targeted Sep 2026. Actual GPU deployment contracted.
Phases
BTM-1 Phase 1 · Under construction18 MW, target 2026
Who is behind it
OperatorNeutraDC Nxera Batam · Joint venture
Funder, Joint venture partnerTelkom Indonesia
Funder, Joint venture partnerSingtel
Funder, Joint venture partnerMedco Power
Client, confirmedGorilla Technology
Money at this site
Announced investment, 2025-10IDR 1.4tn (about US$86m)
Platform deals that include it
Gorilla Technology US$2.5bn five-year GPUaaS contract at NeutraDC Nxera Batam
Anchor lease, 2026-06US$2.5bn
Platform capital spans several sites. It is never added to this project's own figure.
Land
Industrial estateKawasan Industri Terpadu Kabil (Kabil Integrated Industrial Estate) · 8 ha · Jun 2024 Reported source ↗ Telkom's July 2023 release gave the site as 5 ha, so the area is uncertain.
Power supply
Grid supplyPLN Batam · 90 MVA · Oct 2025 Reported source ↗ Premium medium-voltage supply, 90 MVA phased 2025 to 2028, min 5-yr contract, Kabil (PT Teknologi Data Infrastruktur = NeutraDC Nxera Batam)
Renewable power dealMedco Power · 60 MW · Jul 2025 Reported source ↗ Solar, MoU stage · MoU only; solar around Kabil Integrated Industrial Estate for 60MW IT load