How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderNo
Disclosed client (confirmed)Yes
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsNo
AI workloads
StatusConfirmed
Firmus to deploy a 170,000-GPU cluster here (Grace Blackwell / Vera Rubin / Vera AI), rolling out through 2027-2028 under an Nvidia agreement running to 2034 (DCD, 29 Jun 2026).
Who is behind it
OperatorDayOne (PT Digitalland Service One) · Colocation
Client, confirmedFirmus
Platform deals that include it
DayOne / PLN Batam 511 MVA (~450MW) power purchase agreement
Power deal, 2026-04Not disclosed
Firmus x Nvidia 170,000-GPU deployment at DayOne Batam
Anchor lease, 2026-06Not disclosed
Platform capital spans several sites. It is never added to this project's own figure.
Land
Allocated byKabil Industrial Tech Park (BP Batam allocation) · Apr 2026 Reported source ↗ Power supply
Green tariffPLN Batam · Aug 2026 Confirmed source ↗ Ground-mounted or floating solar plus BESS, capacity not stated · Head of Agreement with PT Digitalland Services One (DayOne) for green energy; covers DayOne Batam, site not specified (also NDP) · Covers the operator's wider portfolio in this country, not this site alone.
Grid supplyPLN Batam · 511 MVA · Apr 2026 Confirmed source ↗ Supply agreement with BP Batam as third party; delivered in phases 2026 to 2027 · Applies to the whole campus.
Water and cooling
WaterDesalinated seawater · DayOne-built plant, handed to BP Batam Reported source ↗ BP Batam made the desalination plant a condition of approval because of island water stress