How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsNo
AI workloads
StatusConfirmed
liquid-cooling capable per operator
Phases
Phase 1 (NTP1-3) · Operational70 MW, target 2023
Who is behind it
OperatorDayOne (ex-GDS International) · Colocation
Funder, EquityHillhouse Investment
Funder, EquityBoyu Capital
Funder, DebtBank syndicate (US$3.6B Johor loan, 2025)
Client, reported, unconfirmedByteDance
Client, reported, unconfirmedOracle
Money at this site
Announced investment, 2022-04RM1.38bn (about US$330m)
The figure covers the whole campus.
Platform deals that include it
DayOne Johor syndicated financing
Platform capital, 2025-06US$3.6bn
GDS Johor 10-year commitment
Country programme, 2021-08US$981m
DayOne Series C
Platform capital, 2026-06-05US$4.5bn
Platform capital spans several sites. It is never added to this project's own figure.
Power supply
Renewable power dealTNB Renewables Sdn Bhd · 500 MW · Jun 2025 Confirmed source ↗ CRESS, TNB-developed solar, 21-year term · Platform deal covering DayOne NTP and KTP campuses · Covers the operator's wider portfolio in this country, not this site alone.
Renewable power dealTenaga Nasional Berhad (TNB) / TNB Renewables · Jun 2026 Confirmed source ↗ Over 1GW RE: ~1.5GWp ground-mounted and hybrid hydro floating solar plus 2.2GWh BESS, with RECs · Platform deal covering NTP and KTP; builds on June 2025 500MW CRESS · Covers the operator's wider portfolio in this country, not this site alone.
Virtual renewable dealCenergi SEA · 22.5 MW · Feb 2024 Reported source ↗ 22.5MWac of a 29.99MWac solar farm under CGPP, 21 years · Signed by GDS (DayOne predecessor) for NTP
Grid supplyTenaga Nasional Berhad (TNB) · 85.5 MW · Oct 2022 Reported source ↗ ESA Oct 2022; 16MW interim supply from Jul 2023, max demand rising to 85.5MW