ArusGridProject
Directory › Malaysia › YTL Green Data Center Park

YTL Green Data Center Park

Kulai, Johor, Malaysia · Johor market · location approximate to city level

YTL Green Data Center Park is a data center project in Kulai, Malaysia, operated by YTL Power (YTL Data Center Holdings). It is operational and expanding. It is planned for 500 MW of IT load. The operator reports 150 MW running.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
500 MW
Running now
150 MW
Operators rarely publish this
Operator
YTL Power (YTL Data Center Holdings)
Colocation
AI workloads
Confirmed
Evidence grade
Verified

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

Nvidia GB200 NVL72 deployed, liquid-cooled (Oct 2025)

Phases

JDC1 (colo, Sea anchor) · Operational48 MW, target 2024
JDC2 (Nvidia GB200 AI DC, YTL AI Cloud) · Operational20 MW, target 2025
JDC3 (2nd AI DC) · Under constructionSize not published
JDC6 (built-to-suit MNC) · Operational40 MW, target 2025

Who is behind it

OperatorYTL Power (YTL Data Center Holdings) · Colocation
Funder, EquityYTL Power International
Client, confirmedSea Ltd

Money at this site

Announced investment, 2022-08RM15bn (about US$3.3bn)

The figure covers the whole campus.

Platform deals that include it

YTL-Nvidia AI infrastructure deal
Platform capital, 2023-12
US$2.2bn

Platform capital spans several sites. It is never added to this project's own figure.

Land
Land sellerBoustead Plantations · 664 ha · RM428.8m (≈US$97m) · Sep 2021 Confirmed source ↗
Five parcels, buyer SIPP Power (70% YTL Power)
Power supply
Grid supplyNational grid (TNB) · 600 MW · Nov 2025 Reported source ↗
500MW solar plant planned on site · 600MW from national grid as backup to solar · Applies to the whole campus.
Own generationSIPP Power (YTL Power) and TNB · 215 MW · Jun 2026 Reported source ↗
Co-located solar, about 215MW by end-2026 and 600MW long term · Applies to the whole campus.
Water and cooling
CoolingDirect liquid cooling Reported source ↗
Liquid-cooled Nvidia GB200 NVL72 systems (facility-stated)

Sources checked 2026-09-11

  1. theedgemalaysia.com
  2. datacenterdynamics.com
  3. datacentermap.com
  4. thestar.com.my
  5. YTL Power and JLand Group Collaborate on New Gigawatt-Scale Data Centre Campus at Sedenak Tech Park (YTL Power International, 2026-08-19)

More in Johor

Also run by YTL

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-26.